PISD 2004 Bond Program<br />

Program Administrator: Jacobs<br />

Program Manager: Terry Page<br />

Understanding the<br />

Monthly Report<br />

Bid Package Summary part 1 (Schedule)<br />

Schedule Phase<br />

Design – Programming & Design through<br />

Construction Documents.<br />

Bid & Award – Bidding or in the Award process.<br />

Construction – Construction work in progress.<br />

Move-In – Occupancy is permitted, though minor<br />

activities or corrections continue.<br />

Schedule Data<br />

Plan Start and Finish – Original start and finish<br />

dates. Plan Schedule is the baseline start and<br />

finish dates. These dates are held static<br />

throughout the project, and future schedule<br />

updates are measured against this baseline.<br />

Forecast Start and Finish – Anticipated start<br />

and finish dates. The Forecast Dates will be<br />

updated if schedule changes occur.<br />

Understanding the Monthly Report<br />

Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />

Page 5 of 45