May-2009 - Pasadena Independent School District
May-2009 - Pasadena Independent School District
May-2009 - Pasadena Independent School District
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
PISD 2004 Bond Program<br />
Program Administrator: Jacobs<br />
Program Manager: Terry Page<br />
Understanding the<br />
Monthly Report<br />
Bid Package Summary part 1 (Schedule)<br />
Schedule Phase<br />
Design – Programming & Design through<br />
Construction Documents.<br />
Bid & Award – Bidding or in the Award process.<br />
Construction – Construction work in progress.<br />
Move-In – Occupancy is permitted, though minor<br />
activities or corrections continue.<br />
Schedule Data<br />
Plan Start and Finish – Original start and finish<br />
dates. Plan Schedule is the baseline start and<br />
finish dates. These dates are held static<br />
throughout the project, and future schedule<br />
updates are measured against this baseline.<br />
Forecast Start and Finish – Anticipated start<br />
and finish dates. The Forecast Dates will be<br />
updated if schedule changes occur.<br />
Understanding the Monthly Report<br />
Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />
Page 5 of 45