PISD 2004 Bond Program<br />
Program Administrator: Jacobs<br />
Program Manager: Terry Page<br />
Understanding the<br />
Monthly Report<br />
Program Summary<br />
Overall Program Schedule Status<br />
Number of <strong>School</strong>s by Schedule Phase – A<br />
summary of all schools status data. Each school<br />
is designated by a status:<br />
• Not Started – No design or<br />
construction activities have begun.<br />
• Design – Programming & Design<br />
through Construction Documents.<br />
• Bid & Award – Bidding or in the award<br />
process.<br />
• Construction – Construction work in<br />
progress.<br />
• Move-In – Occupancy is permitted,<br />
though minor activities or corrections<br />
continue.<br />
• Complete – All work is done, final<br />
submittals are complete and final<br />
payment authorized.<br />
Value of <strong>School</strong>s by Schedule Phase – A<br />
summary of the Total Project Budgets of the<br />
schools grouped per designated Scheduled<br />
Phase.<br />
Understanding the Monthly Report<br />
Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />
Page 3 of 45