PISD 2004 <strong>School</strong> Bond Program<br />
Program Manager: Terry Page<br />
Project Manager: Veronica Leonce<br />
Project Architect: Randall-Porterfield<br />
General Contractor: Durotech<br />
Location: 8420 Easthaven Blvd.<br />
Project Summary<br />
Schneider MS<br />
Bid Package 01<br />
New <strong>School</strong>s and Renovations<br />
Cost Description<br />
Original<br />
Budget<br />
Budget<br />
Adjustments<br />
Current<br />
Budget<br />
Committed<br />
Costs<br />
Cost to Date<br />
Balance<br />
Estimate at<br />
Completion<br />
Construction $13,280,000 ($744,416) $12,535,584 $12,535,584 $12,535,584 $0 $12,535,584<br />
Design A/E $584,320 $276,443 $860,763 $860,763 $860,763 $0 $860,763<br />
FF&E $982,696 ($62,586) $920,110 $920,110 $920,110 $0 $920,110<br />
Asbestos $26,500 ($26,073) $427 $427 $427 $0 $427<br />
Construction-Other $372,373 $56,456 $428,829 $428,829 $428,829 $0 $428,829<br />
Project Contingency $1,098,343 $458,148 $1,556,491 $1,556,491 $1,556,491 $0 $1,556,491<br />
Professional Services-Other $255,768 ($689) $255,079 $255,079 $242,654 $0 $255,079<br />
Miscellaneous $0 $0 $0 $0 $0 $0 $0<br />
Budget<br />
Balance<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
Totals: $16,600,000 ($42,717) $16,557,283 $16,557,283 $16,544,858 $0 $16,557,283 $0<br />
Project Notes<br />
1. Major Activities:<br />
The project is complete.<br />
2. Key Issues and Concerns:<br />
The remaining HVAC issues are being completed by UES; PM has<br />
requested a completion schedule.<br />
$18,000,000<br />
$16,200,000<br />
$14,400,000<br />
$12,600,000<br />
$10,800,000<br />
$9,000,000<br />
$7,200,000<br />
$5,400,000<br />
$3,600,000<br />
$1,800,000<br />
$0<br />
Current<br />
Budget<br />
Committed<br />
Costs<br />
Cost to<br />
Date<br />
Estimate at<br />
Completion<br />
Schneider MS<br />
Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />
Page 15 of 45