PISD 2004 <strong>School</strong> Bond Program<br />

Program Manager: Terry Page<br />

Project Manager: Veronica Leonce<br />

Project Architect: Randall-Porterfield<br />

General Contractor: Durotech<br />

Location: 8420 Easthaven Blvd.<br />

Project Summary<br />

Schneider MS<br />

Bid Package 01<br />

New <strong>School</strong>s and Renovations<br />

Cost Description<br />

Original<br />

Budget<br />

Budget<br />

Adjustments<br />

Current<br />

Budget<br />

Committed<br />

Costs<br />

Cost to Date<br />

Balance<br />

Estimate at<br />

Completion<br />

Construction $13,280,000 ($744,416) $12,535,584 $12,535,584 $12,535,584 $0 $12,535,584<br />

Design A/E $584,320 $276,443 $860,763 $860,763 $860,763 $0 $860,763<br />

FF&E $982,696 ($62,586) $920,110 $920,110 $920,110 $0 $920,110<br />

Asbestos $26,500 ($26,073) $427 $427 $427 $0 $427<br />

Construction-Other $372,373 $56,456 $428,829 $428,829 $428,829 $0 $428,829<br />

Project Contingency $1,098,343 $458,148 $1,556,491 $1,556,491 $1,556,491 $0 $1,556,491<br />

Professional Services-Other $255,768 ($689) $255,079 $255,079 $242,654 $0 $255,079<br />

Miscellaneous $0 $0 $0 $0 $0 $0 $0<br />

Budget<br />

Balance<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

Totals: $16,600,000 ($42,717) $16,557,283 $16,557,283 $16,544,858 $0 $16,557,283 $0<br />

Project Notes<br />

1. Major Activities:<br />

The project is complete.<br />

2. Key Issues and Concerns:<br />

The remaining HVAC issues are being completed by UES; PM has<br />

requested a completion schedule.<br />

$18,000,000<br />

$16,200,000<br />

$14,400,000<br />

$12,600,000<br />

$10,800,000<br />

$9,000,000<br />

$7,200,000<br />

$5,400,000<br />

$3,600,000<br />

$1,800,000<br />

$0<br />

Current<br />

Budget<br />

Committed<br />

Costs<br />

Cost to<br />

Date<br />

Estimate at<br />

Completion<br />

Schneider MS<br />

Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />

Page 15 of 45