May-2009 - Pasadena Independent School District
May-2009 - Pasadena Independent School District
May-2009 - Pasadena Independent School District
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
PISD 2004 <strong>School</strong> Bond Program<br />
Program Manager: Terry Page<br />
Project Manager: Katrina McDaniel<br />
Project Architect: Randall-Porterfield<br />
General Contractor: Brothers<br />
Location: 101 E. Jackson<br />
Project Summary<br />
De Zavala Middle <strong>School</strong><br />
Bid Package 24<br />
New <strong>School</strong>s and Renovations<br />
Cost Description<br />
Original<br />
Budget<br />
Budget<br />
Adjustments<br />
Current<br />
Budget<br />
Committed<br />
Costs<br />
Cost to Date<br />
Balance<br />
Estimate at<br />
Completion<br />
Construction $0 $3,353,453 $3,353,453 $3,263,453 $943,798 $90,000 $3,353,453<br />
Design A/E $0 $271,340 $271,340 $254,709 $218,694 $16,631 $271,340<br />
FF&E $0 $164,760 $164,760 $0 $0 $164,760 $164,760<br />
Asbestos $0 $0 $0 $0 $0 $0 $0<br />
Construction-Other $0 $113,645 $113,645 $95,556 $17,355 $18,089 $113,645<br />
Project Contingency $0 $218,716 $218,716 $0 $0 $218,716 $218,716<br />
Professional Services-Other $0 $78,086 $78,086 $57,988 $20,244 $20,098 $78,086<br />
Miscellaneous $0 $0 $0 $0 $0 $0 $0<br />
Budget<br />
Balance<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
Totals: $0 $4,200,000 $4,200,000 $3,671,706 $1,200,091 $528,294 $4,200,000 $0<br />
Project Notes<br />
1. Major Activities:<br />
The GC is working on overhead mechanical and electrical in the<br />
classroom addition. They have completed the slab pour and are<br />
scheduled to begin steel erection in the library/cafeteria addition at the<br />
end of <strong>May</strong> <strong>2009</strong>.<br />
2. Key Issues and Concerns:<br />
Continued progress of the construction schedule is critical for the<br />
August <strong>2009</strong> opening for the classroom and library/cafeteria additions.<br />
$4,500,000<br />
$4,050,000<br />
$3,600,000<br />
$3,150,000<br />
$2,700,000<br />
$2,250,000<br />
$1,800,000<br />
$1,350,000<br />
$900,000<br />
$450,000<br />
$0<br />
Current<br />
Budget<br />
Committed<br />
Costs<br />
Cost to<br />
Date<br />
Estimate at<br />
Completion<br />
De Zavala Middle <strong>School</strong><br />
Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />
Page 43 of 45