PISD 2004 <strong>School</strong> Bond Program<br />

Program Manager: Terry Page<br />

Project Manager: Katrina McDaniel<br />

Project Architect: Randall-Porterfield<br />

General Contractor: Brothers<br />

Location: 101 E. Jackson<br />

Project Summary<br />

De Zavala Middle <strong>School</strong><br />

Bid Package 24<br />

New <strong>School</strong>s and Renovations<br />

Cost Description<br />

Original<br />

Budget<br />

Budget<br />

Adjustments<br />

Current<br />

Budget<br />

Committed<br />

Costs<br />

Cost to Date<br />

Balance<br />

Estimate at<br />

Completion<br />

Construction $0 $3,353,453 $3,353,453 $3,263,453 $943,798 $90,000 $3,353,453<br />

Design A/E $0 $271,340 $271,340 $254,709 $218,694 $16,631 $271,340<br />

FF&E $0 $164,760 $164,760 $0 $0 $164,760 $164,760<br />

Asbestos $0 $0 $0 $0 $0 $0 $0<br />

Construction-Other $0 $113,645 $113,645 $95,556 $17,355 $18,089 $113,645<br />

Project Contingency $0 $218,716 $218,716 $0 $0 $218,716 $218,716<br />

Professional Services-Other $0 $78,086 $78,086 $57,988 $20,244 $20,098 $78,086<br />

Miscellaneous $0 $0 $0 $0 $0 $0 $0<br />

Budget<br />

Balance<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

Totals: $0 $4,200,000 $4,200,000 $3,671,706 $1,200,091 $528,294 $4,200,000 $0<br />

Project Notes<br />

1. Major Activities:<br />

The GC is working on overhead mechanical and electrical in the<br />

classroom addition. They have completed the slab pour and are<br />

scheduled to begin steel erection in the library/cafeteria addition at the<br />

end of <strong>May</strong> <strong>2009</strong>.<br />

2. Key Issues and Concerns:<br />

Continued progress of the construction schedule is critical for the<br />

August <strong>2009</strong> opening for the classroom and library/cafeteria additions.<br />

$4,500,000<br />

$4,050,000<br />

$3,600,000<br />

$3,150,000<br />

$2,700,000<br />

$2,250,000<br />

$1,800,000<br />

$1,350,000<br />

$900,000<br />

$450,000<br />

$0<br />

Current<br />

Budget<br />

Committed<br />

Costs<br />

Cost to<br />

Date<br />

Estimate at<br />

Completion<br />

De Zavala Middle <strong>School</strong><br />

Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />

Page 43 of 45