PISD 2004 <strong>School</strong> Bond Program<br />
Program Manager: Terry Page<br />
Project Manager: Veronica Leonce<br />
Project Architect: SBWV<br />
General Contractor: Cadence McShane<br />
Location: 3600 Red Bluff<br />
Project Summary<br />
San Jacinto Replacement Int.<br />
Bid Package 04<br />
New <strong>School</strong>s and Renovations<br />
Cost Description<br />
Original<br />
Budget<br />
Budget<br />
Adjustments<br />
Current<br />
Budget<br />
Committed<br />
Costs<br />
Cost to Date<br />
Balance<br />
Estimate at<br />
Completion<br />
Construction $19,600,000 ($1,971,976) $17,628,024 $17,481,176 $17,355,792 $146,848 $17,628,024<br />
Design A/E $1,315,160 ($28,220) $1,286,940 $1,281,088 $1,257,176 $5,852 $1,286,940<br />
FF&E $1,076,100 ($37,826) $1,038,274 $875,649 $875,649 $162,625 $1,038,274<br />
Asbestos $41,800 ($40,065) $1,735 $1,735 $1,735 $0 $1,735<br />
Construction-Other $571,446 ($10,105) $561,341 $509,679 $356,371 $51,661 $561,341<br />
Project Contingency $1,567,218 ($1,536,027) $31,191 $0 $0 $31,191 $31,191<br />
Professional Services-Other $328,276 ($56,780) $271,496 $259,203 $255,380 $12,293 $271,496<br />
Miscellaneous $0 $0 $0 $0 $0 $0 $0<br />
Budget<br />
Balance<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
Totals: $24,500,000 ($3,681,000) $20,819,000 $20,408,530 $20,102,104 $410,470 $20,819,000 $0<br />
Project Notes<br />
1. Major Activities:<br />
The general contractor is working on punch list items and performing<br />
warranty work at this time. PISD is back checking completed areas.<br />
2. Key Issues and Concerns:<br />
Replacement of parts of the gym floor, completion of the punch list<br />
and a timely close out.<br />
$21,000,000<br />
$18,900,000<br />
$16,800,000<br />
$14,700,000<br />
$12,600,000<br />
$10,500,000<br />
$8,400,000<br />
$6,300,000<br />
$4,200,000<br />
$2,100,000<br />
$0<br />
Current<br />
Budget<br />
Committed<br />
Costs<br />
Cost to<br />
Date<br />
Estimate at<br />
Completion<br />
San Jacinto Replacement Int.<br />
Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />
Page 19 of 45