PISD 2004 <strong>School</strong> Bond Program<br />

Program Manager: Terry Page<br />

Project Manager: Katrina McDaniel<br />

Project Architect: Dansby Miller<br />

General Contractor: DT Construction<br />

Project Summary<br />

Phase 1C-Bondy IS,Bailey,SHES & Beverly<br />

Bid Package 13<br />

New <strong>School</strong>s and Renovations<br />

Cost Description<br />

Original<br />

Budget<br />

Budget<br />

Adjustments<br />

Current<br />

Budget<br />

Committed<br />

Costs<br />

Cost to Date<br />

Balance<br />

Estimate at<br />

Completion<br />

Construction $2,910,330 ($734,972) $2,175,358 $2,175,358 $2,175,358 $0 $2,175,358<br />

Design A/E $239,671 ($12,630) $227,041 $227,041 $227,041 $0 $227,041<br />

FF&E $67,333 $8,055 $75,388 $66,502 $66,502 $8,886 $75,388<br />

Asbestos $17,273 $3,551 $20,824 $20,824 $20,824 $0 $20,824<br />

Construction-Other $27,575 $83,585 $111,160 $111,160 $111,160 $0 $111,160<br />

Project Contingency $191,974 ($178,124) $13,850 $0 $0 $13,850 $13,850<br />

Professional Services-Other $43,861 ($3,465) $40,396 $40,396 $40,396 $0 $40,396<br />

Miscellaneous $0 $0 $0 $0 $0 $0 $0<br />

Budget<br />

Balance<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

Totals: $3,498,017 ($834,000) $2,664,017 $2,641,281 $2,641,281 $22,736 $2,664,017 $0<br />

Project Notes<br />

1. Major Activities:<br />

Project closeout is complete.<br />

2. Key Issues and Concerns:<br />

None at this time.<br />

$2,700,000<br />

$2,430,000<br />

$2,160,000<br />

$1,890,000<br />

$1,620,000<br />

$1,350,000<br />

$1,080,000<br />

$810,000<br />

$540,000<br />

$270,000<br />

$0<br />

Current<br />

Budget<br />

Committed<br />

Costs<br />

Cost to<br />

Date<br />

Estimate at<br />

Completion<br />

Phase 1C-Bondy IS,Bailey,SHES & Beverly Aud.<br />

Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />

Page 33 of 45