PISD 2004 <strong>School</strong> Bond Program<br />
Program Manager: Terry Page<br />
Project Manager: Chris Koeper<br />
Project Architect: Bay<br />
General Contractor: Brae Burn Construction<br />
Location: 1801 Riverstone Ranch Drive<br />
Project Summary<br />
South Belt ES<br />
Bid Package 06<br />
New <strong>School</strong>s and Renovations<br />
Cost Description<br />
Original<br />
Budget<br />
Budget<br />
Adjustments<br />
Current<br />
Budget<br />
Committed<br />
Costs<br />
Cost to Date<br />
Balance<br />
Estimate at<br />
Completion<br />
Construction $11,040,000 $1,600,656 $12,640,656 $12,387,451 $10,549,627 $253,205 $12,640,656<br />
Design A/E $740,744 ($231,800) $508,944 $491,816 $467,087 $17,128 $508,944<br />
FF&E $871,776 $0 $871,776 $290,167 $286,982 $581,609 $871,776<br />
Asbestos $0 $0 $0 $0 $0 $0 $0<br />
Construction-Other $269,876 $373,582 $643,458 $597,070 $365,527 $46,388 $643,458<br />
Project Contingency $676,019 ($302,862) $373,157 $0 $0 $373,157 $373,157<br />
Professional Services-Other $201,585 $46,924 $248,509 $223,052 $154,296 $25,457 $248,509<br />
Misc $0 $100,000 $100,000 $97,250 $97,250 $2,750 $100,000<br />
Budget<br />
Balance<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
Totals: $13,800,000 $1,586,500 $15,386,500 $14,086,806 $11,920,768 $1,299,694 $15,386,500 $0<br />
Project Notes<br />
1. Major Activities:<br />
The GC continues with MEP through Area C (cafeteria, gym and<br />
music rooms). Interior finishes are ongoing. Final paint and VCT<br />
flooring has commenced in Area B (classrooms). Above ceiling<br />
inspections are complete in Area B and Area A; the GC is addressing<br />
the above ceiling deficiencies.<br />
2. Key Issues and Concerns:<br />
Contractor appears to be approximately 2-3 weeks behind schedule.<br />
Part of this is due to late install of permanent power by CenterPoint.<br />
$16,000,000<br />
$14,400,000<br />
$12,800,000<br />
$11,200,000<br />
$9,600,000<br />
$8,000,000<br />
$6,400,000<br />
$4,800,000<br />
$3,200,000<br />
$1,600,000<br />
$0<br />
Current<br />
Budget<br />
Committed<br />
Costs<br />
Cost to<br />
Date<br />
Estimate at<br />
Completion<br />
South Belt ES<br />
Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />
Page 23 of 45