PISD 2004 <strong>School</strong> Bond Program<br />

Program Manager: Terry Page<br />

Project Manager: Chris Koeper<br />

Project Architect: Bay<br />

General Contractor: Brae Burn Construction<br />

Location: 1801 Riverstone Ranch Drive<br />

Project Summary<br />

South Belt ES<br />

Bid Package 06<br />

New <strong>School</strong>s and Renovations<br />

Cost Description<br />

Original<br />

Budget<br />

Budget<br />

Adjustments<br />

Current<br />

Budget<br />

Committed<br />

Costs<br />

Cost to Date<br />

Balance<br />

Estimate at<br />

Completion<br />

Construction $11,040,000 $1,600,656 $12,640,656 $12,387,451 $10,549,627 $253,205 $12,640,656<br />

Design A/E $740,744 ($231,800) $508,944 $491,816 $467,087 $17,128 $508,944<br />

FF&E $871,776 $0 $871,776 $290,167 $286,982 $581,609 $871,776<br />

Asbestos $0 $0 $0 $0 $0 $0 $0<br />

Construction-Other $269,876 $373,582 $643,458 $597,070 $365,527 $46,388 $643,458<br />

Project Contingency $676,019 ($302,862) $373,157 $0 $0 $373,157 $373,157<br />

Professional Services-Other $201,585 $46,924 $248,509 $223,052 $154,296 $25,457 $248,509<br />

Misc $0 $100,000 $100,000 $97,250 $97,250 $2,750 $100,000<br />

Budget<br />

Balance<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

Totals: $13,800,000 $1,586,500 $15,386,500 $14,086,806 $11,920,768 $1,299,694 $15,386,500 $0<br />

Project Notes<br />

1. Major Activities:<br />

The GC continues with MEP through Area C (cafeteria, gym and<br />

music rooms). Interior finishes are ongoing. Final paint and VCT<br />

flooring has commenced in Area B (classrooms). Above ceiling<br />

inspections are complete in Area B and Area A; the GC is addressing<br />

the above ceiling deficiencies.<br />

2. Key Issues and Concerns:<br />

Contractor appears to be approximately 2-3 weeks behind schedule.<br />

Part of this is due to late install of permanent power by CenterPoint.<br />

$16,000,000<br />

$14,400,000<br />

$12,800,000<br />

$11,200,000<br />

$9,600,000<br />

$8,000,000<br />

$6,400,000<br />

$4,800,000<br />

$3,200,000<br />

$1,600,000<br />

$0<br />

Current<br />

Budget<br />

Committed<br />

Costs<br />

Cost to<br />

Date<br />

Estimate at<br />

Completion<br />

South Belt ES<br />

Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />