PISD 2004 <strong>School</strong> Bond Program<br />
Program Manager: Terry Page<br />
Project Manager: Crystal Gomez<br />
Project Architect: Bay<br />
General Contractor: Skanska<br />
Location: 610 South Richey<br />
Project Summary<br />
Richey Replacement ES<br />
Bid Package 09A<br />
New <strong>School</strong>s and Renovations<br />
Cost Description<br />
Original<br />
Budget<br />
Budget<br />
Adjustments<br />
Current<br />
Budget<br />
Committed<br />
Costs<br />
Cost to Date<br />
Balance<br />
Estimate at<br />
Completion<br />
Construction $11,040,000 $391,310 $11,431,310 $11,162,064 $11,162,064 $269,245 $11,431,310<br />
Design A/E $485,760 ($20,000) $465,760 $461,322 $452,490 $4,438 $465,760<br />
FF&E $563,600 ($15,000) $548,600 $538,329 $538,072 $10,271 $548,600<br />
Asbestos $52,000 $267,746 $319,746 $319,746 $233,418 $0 $319,746<br />
Construction-Other $769,876 ($222,816) $547,060 $546,251 $509,184 $809 $547,060<br />
Project Contingency $697,209 ($696,769) $440 $0 $0 $440 $440<br />
Professional Services-Other $191,555 ($19,470) $172,085 $171,504 $166,249 $581 $172,085<br />
Miscellaneous $0 $0 $0 $0 $0 $0 $0<br />
Budget<br />
Balance<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
Totals: $13,800,000 ($315,000) $13,485,000 $13,199,217 $13,061,477 $285,783 $13,485,000 $0<br />
Project Notes<br />
1. Major Activities:<br />
The GC provided a credit dollar amount for the incomplete punch list<br />
items; PISD accepted the offer and is reviewing possible vendors to<br />
complete the punch list. KBR has completed the curb inlets at the<br />
cul-de-sac; work requested by the City of <strong>Pasadena</strong> (CoP). CoP Fire<br />
Marshall requested the school entry drive be widened to provide fire<br />
truck access; KBR has been requested to submit a quote for this work.<br />
2. Key Issues and Concerns:<br />
Ensuring the revisions to the entry drive is completed over Summer<br />
<strong>2009</strong>.<br />
$14,000,000<br />
$12,600,000<br />
$11,200,000<br />
$9,800,000<br />
$8,400,000<br />
$7,000,000<br />
$5,600,000<br />
$4,200,000<br />
$2,800,000<br />
$1,400,000<br />
$0<br />
Current<br />
Budget<br />
Committed<br />
Costs<br />
Cost to<br />
Date<br />
Estimate at<br />
Completion<br />
Richey Replacement ES<br />
Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />