PISD 2004 Bond Program<br />
Program Administrator: Jacobs<br />
Program Manager: Terry Page<br />
Phone: 713-740-0882<br />
Cell: 281-808-8550<br />
Executive Summary<br />
2004 Bond Original Budget: $299,880,000 Current Budget with Infusions and Interest: $315,696,633<br />
Program Description:<br />
Jacobs is providing design coordination, budget and cost control, program scheduling, construction coordination and oversight for the <strong>Pasadena</strong><br />
<strong>Independent</strong> <strong>School</strong> <strong>District</strong>’s 2004 Bond Program. The 2004 Bond Program includes fourteen (14) new schools: 5 Elementary, 5 Middle, 2<br />
Intermediate and 2 High <strong>School</strong> additions totaling $214,180,000; forty three (43) renovations totaling $33,080,000; and other projects: Summit and<br />
Technology Center, Satellite Transportation Center, Portables, Security Cameras for elementary schools and Technology additions totaling<br />
$20,400,000. The remaining amount of $32,220,000 will be spent on Buses, Land Acquisition and Program Management services.<br />
Program Status:<br />
The following is a list of schools that are currently under the Design, Bid and Award, Construction, and Substantially Complete phases.<br />
Design:<br />
None<br />
Bid and Award:<br />
None<br />
Construction:<br />
BP-06-South Belt Elementary <strong>School</strong><br />
BP-08-Kruse Replacement Elementary <strong>School</strong><br />
Substantially Complete:<br />
BP-04-San Jacinto Replacement Intermediate <strong>School</strong><br />
BP-04A-Southmore Replacement Intermediate <strong>School</strong><br />
BP-07- Dr. Dixie Melillo Middle <strong>School</strong><br />
Complete:<br />
BP-01-Schneider Middle <strong>School</strong><br />
BP-02-Bush Elementary <strong>School</strong><br />
BP-03-<strong>Pasadena</strong> Memorial High <strong>School</strong> Additions and Renovations<br />
BP-03A-Dobie High <strong>School</strong> Additions and Renovations<br />
BP-05-Milstead Middle <strong>School</strong><br />
BP-05A-Lomax Middle <strong>School</strong><br />
BP-07-Hughes Road Extension<br />
BP-09-Pearl Hall Replacement Elementary <strong>School</strong><br />
BP-11-1A-Guidance Center<br />
BP-12-1B-PHS & Sam Rayburn<br />
BP-13-1C-Bondy IS, Bailey ES, South Houston ES & Beverly IS<br />
BP-14-1D-South Houston HS Auditorium/Renovations<br />
BP-24-De Zavala Middle <strong>School</strong><br />
BP-09A-Richey Replacement Elementary <strong>School</strong><br />
BP-10-Bobby Shaw Area Middle <strong>School</strong><br />
BP-22-Phillips Gym/Veterans Memorial Stadium<br />
BP-15-2A-Meador ES, LF Smith ES, Freeman ES, Fisher ES, Queens Int.<br />
BP-16-2B-Williams ES, Red Bluff ES, Pomeroy ES, Mae Smythe ES, Jessup<br />
ES, Garfield ES, Park View Int., Gardens ES, South Shaver ES, Morris 5 th Grade<br />
BP-17-3A-Young ES, Teague ES, Sparks ES, Moore ES, Stuchbery ES,<br />
McMasters ES, Jensen ES, Atkinson ES Thompson IS, Miller IS<br />
BP-18-Turner ES, Matthys ES, Frazier ES, Burnett ES, Tegeler Career Center,<br />
SH Int., Skill Center and Blackhawk Rd. Warehouse<br />
BP-19-3C-Morales ES Renovation, Parks ES<br />
BP-20-Portables 2005-06 and BP-20-Portables 2006-07<br />
BP-21-1E-Summit - Tech. Center<br />
BP-22A-Transportation Center<br />
Executive Summary<br />
Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />
Page 7 of 45