PISD 2004 <strong>School</strong> Bond Program<br />
Program Manager: Terry Page<br />
Project Manager: George Lloyd<br />
Project Architect: Cre8<br />
General Contractor: Brothers Construction<br />
Location: 2906 Dabney<br />
Project Summary<br />
Phase 3D-Phillips Gym/Veterans Memorial<br />
Bid Package 22<br />
New <strong>School</strong>s and Renovations<br />
Cost Description<br />
Original<br />
Budget<br />
Budget<br />
Adjustments<br />
Current<br />
Budget<br />
Committed<br />
Costs<br />
Cost to Date<br />
Balance<br />
Estimate at<br />
Completion<br />
Construction $1,177,960 $588,477 $1,766,437 $1,766,437 $1,766,437 $0 $1,766,437<br />
Design A/E $97,007 $2,318 $99,325 $99,325 $97,244 $0 $99,325<br />
FF&E $79,958 $0 $79,958 $30,958 $30,958 $49,000 $79,958<br />
Asbestos $0 $8,959 $8,959 $8,959 $8,959 $0 $8,959<br />
Construction-Other $24,105 ($4,334) $19,771 $19,771 $19,771 $0 $19,771<br />
Project Contingency $15,130 ($10,698) $4,432 $0 $0 $4,432 $4,432<br />
Professional Services-Other $21,665 ($723) $20,942 $20,942 $20,442 $0 $20,942<br />
Miscellaneous $0 $0 $0 $0 $0 $0 $0<br />
Budget<br />
Balance<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
Totals: $1,415,825 $584,000 $1,999,825 $1,946,393 $1,943,811 $53,432 $1,999,825 $0<br />
Project Notes<br />
1. Major Activities:<br />
Warranty replacement of floor sealant is complete. Final punch list<br />
back check is scheduled for week of <strong>May</strong> 11, <strong>2009</strong>.<br />
2. Key Issues and Concerns:<br />
None at this time.<br />
$2,000,000<br />
$1,800,000<br />
$1,600,000<br />
$1,400,000<br />
$1,200,000<br />
$1,000,000<br />
$800,000<br />
$600,000<br />
$400,000<br />
$200,000<br />
$0<br />
Current<br />
Budget<br />
Committed<br />
Costs<br />
Cost to<br />
Date<br />
Estimate at<br />
Completion<br />
Phase 3D-Phillips Gym/Veterans Memorial Stadium<br />
Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />
Page 41 of 45