Los Angeles Harbor Department Section 2 <strong>Mitigation</strong> <strong>Monitoring</strong> <strong>and</strong> <strong>Reporting</strong> <strong>Program</strong><br />

MM AQ-4. Best Management Practices. Timing: Prior to <strong>and</strong> during construction. Implementation: BNSF <strong>and</strong> Alternate Business<br />

Location Tenants through Construction Contractors<br />

The following measures are required on construction<br />

equipment (including onroad trucks):<br />

Methods: This measure shall be incorporated into<br />

BNSF’s <strong>and</strong> Alternate Business Location Tenants’ bid <strong>Monitoring</strong> <strong>and</strong> <strong>Reporting</strong>:<br />

· Use diesel oxidation catalysts <strong>and</strong> catalyzed diesel <strong>and</strong> contract specifications approved by LAHD for all LAHD, Environmental Management Division,<br />

particulate traps.<br />

construction work to reduce the impacts of construction Construction Management Division<br />

· Maintain equipment according to manufacturers’ diesel emissions. The LAHD shall determine the BMPs<br />

specifications.<br />

· Restrict idling of construction equipment to a maximum<br />

once the contractor(s) identifies <strong>and</strong> secures a final<br />

equipment list. The contractor(s) shall adhere to these<br />

of 5 minutes when not in use.<br />

specifications throughout construction phases.<br />

· Install high-pressure fuel injectors on construction Enforcement shall include oversight by BNSF’s <strong>and</strong><br />

equipment vehicles.<br />

LAHD shall implement a process by which to select<br />

Tenants’ project/construction manager or designated<br />

building inspectors to ensure compliance with contract<br />

additional BMPs to further reduce air emissions during specifications.<br />

construction. The LAHD shall determine the BMPs once the<br />

contractor identifies <strong>and</strong> secures a final equipment list.<br />

MM AQ-5. General <strong>Mitigation</strong> Measure. Timing: Prior to <strong>and</strong> during construction. Implementation: BNSF <strong>and</strong> Alternate Business<br />

Location Tenants through Construction Contractors.<br />

For any of the above mitigation measures, if a CARB-certified<br />

technology becomes available <strong>and</strong> is shown to be equal or<br />

Methods: This measure shall be incorporated into the<br />

BNSF’s <strong>and</strong> Tenants’ bid <strong>and</strong> contract specifications <strong>Monitoring</strong> <strong>and</strong> <strong>Reporting</strong>:<br />

more effective in terms of emissions performance than the approved by LAHD. The contractor(s) shall submit a LAHD, Environmental Management Division,<br />

existing measure, the technology could replace the existing<br />

measure pending approval by the LAHD.<br />

plan for review <strong>and</strong> approval by BNSF <strong>and</strong> Tenants<br />

prior to beginning any construction activity, which<br />

would include any proposed new technology.<br />

Construction Management Division<br />

MM AQ-6. Special Precautions near Sensitive Sites. Timing: Prior to <strong>and</strong> during construction. Implementation: BNSF <strong>and</strong> Alternate Business<br />

Location Tenants through Construction Contractors<br />

When construction activities are planned within 1,000 feet of Methods: This measure shall be incorporated into the <strong>Monitoring</strong> <strong>and</strong> <strong>Reporting</strong>:<br />

sensitive receptors (defined as schools, playgrounds, day care BNSF’s <strong>and</strong> Tenants’ bid <strong>and</strong> contract specifications LAHD, Environmental Management Division,<br />

centers, <strong>and</strong> hospitals), the construction contractor shall notify approved by LAHD for all construction activity. The Construction Management Division<br />

each of these sites in writing at least 30 days before contractor(s) shall submit for review <strong>and</strong> approval by<br />

construction activities begin.<br />

BNSF <strong>and</strong> Tenants prior to beginning of any<br />

construction activity, a plan to notify sensitive receptors.<br />

SCIG <strong>Final</strong> EIR 2-8