Los Angeles Harbor Department Section 2 <strong>Mitigation</strong> <strong>Monitoring</strong> <strong>and</strong> <strong>Reporting</strong> <strong>Program</strong><br />

MM PS-3: Solid Waste Management Timing: During Project operation. Implementation: BNSF <strong>and</strong> Tenants<br />

To ensure adequate long-term solid waste management, the<br />

proposed Project will be required to comply with policies <strong>and</strong><br />

st<strong>and</strong>ards set forth in the City’s Solid Waste Integrated<br />

Resources Plan (SWIRP) following 2025.<br />

Methods: This measure shall also be incorporated into<br />

the lease agreements. Bi-annual tenant compliance<br />

reports shall be supplied to the LAHD Environmental<br />

Management Division. Enforcement shall include<br />

oversight by the Real Estate Division.<br />

<strong>Monitoring</strong> <strong>and</strong> <strong>Reporting</strong>:<br />

LAHD, Environmental Management <strong>and</strong> Real Estate<br />

Divisions<br />

Water Resources<br />

MM WR-1a: Dominguez Channel Railroad Bridge Timing: During Project construction. Implementation: BNSF through Construction<br />

Contractors<br />

The following measures shall be implemented during the<br />

reconstruction of the Dominguez Channel Railroad Bridge<br />

1. No construction materials, equipment, debris, or waste<br />

shall be placed or stored where it may be subject to erosion or<br />

could flow into the channel. Construction materials shall not<br />

be stored in contact with the soil.<br />

2. Floating booms shall be used to assist in containing<br />

debris discharged into Dominguez Channel, <strong>and</strong> any debris<br />

discharged shall be removed as soon as possible but no later<br />

than the end of each day.<br />

3. A silt curtain shall be utilized to help control turbidity<br />

during reconstruction of the Dominguez Channel Bridge.<br />

BNSF shall limit, to the greatest extent possible the<br />

suspension of benthic sediments into the water column.<br />

Reasonable <strong>and</strong> prudent measures shall be taken to prevent all<br />

discharge of fuel or oily waste from heavy machinery or<br />

construction equipment or power tools into the Dominguez<br />

Channel. Such measures include deployed oil booms <strong>and</strong> a silt<br />

curtain around the proposed construction zone at all times to<br />

minimize the spread of any accidental fuel spills, turbid<br />

construction-related water discharge, <strong>and</strong> debris; training<br />

construction workers on emergency spill notification<br />

procedures; proper storage of fuels <strong>and</strong> lubricants; <strong>and</strong><br />

provisions for on-site spill response kits.<br />

Methods: This measure shall be incorporated into<br />

BNSF’s bid <strong>and</strong> contract specifications approved by<br />

LAHD. The contractor(s) shall adhere to these<br />

specifications throughout construction phases.<br />

Enforcement shall include oversight by BNSF’s<br />

project/construction managers or designated building<br />

inspectors to ensure compliance with contract<br />

specifications.<br />

<strong>Monitoring</strong> <strong>and</strong> <strong>Reporting</strong>:<br />

LAHD, Environmental Management Division<br />

SCIG <strong>Final</strong> EIR 2-28