Download - Royal Australian Navy
Download - Royal Australian Navy
Download - Royal Australian Navy
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
NAVY ENGINEERING BULLETIN MARCH 2003<br />
41<br />
Engineering Standard 45 and an<br />
associated database and<br />
maintenance management<br />
software package (much like<br />
AMPS). After completing a<br />
functional model of the vessel,<br />
around 15,000 failure modes<br />
were run through the RCM<br />
decision-making process using<br />
teams comprising experienced<br />
staff who had worked closely with<br />
the systems in service and a<br />
range of OEM representatives.<br />
Of the 15,000 failure modes<br />
examined, it was found that just<br />
20% responded to some form of<br />
condition-based maintenance,<br />
whilst ‘traditional’ scheduled<br />
restoration or discard was only<br />
appropriate for just 6% of all<br />
failure modes. A further 18% of<br />
the failure modes required was<br />
associated with protective<br />
devices which required detective<br />
maintenance or ‘failure finding’ as<br />
this is known in RCM. Two thirds<br />
of the failure modes did not<br />
respond to any form of proactive<br />
maintenance activity. These<br />
findings lined up closely with the<br />
experiences of the aviation<br />
industry and reflected the<br />
complexity of systems installed.<br />
The first ship to go to sea with an<br />
RCM-based programme was HMS<br />
ATHERSTONE in April 1998<br />
followed by BROCKLESBY,<br />
LEDBURY and QUORN. All<br />
MCMVs are expected to be<br />
operating on RCM-based<br />
maintenance programmes within<br />
the next year to eighteen months.<br />
Results from the trials can be<br />
divided into three categories:<br />
operational costs, availabilities<br />
and impact on HQ and shorebased<br />
support organisations.<br />
• Operating costs for the RCM<br />
control group showed a 19%<br />
reduction over the period of the<br />
trial amounting to £0.5M per<br />
vessel per annum, despite a<br />
stores supply problem which<br />
pushed up spares cost for the<br />
control group. Discounting this<br />
effect, savings in maintenance<br />
effort for the control group were<br />
33% lower.<br />
• Availabilities of the control group<br />
and the non-RCM vessels were<br />
comparable, although the control<br />
group was negatively influenced<br />
by the stores problem above.<br />
Control group availabilities have<br />
improved as stores processes<br />
have been tackled.<br />
• The most significant changes<br />
have been a shift in maintenance<br />
effort from non-Fleet to Fleet<br />
time, and the removal of large<br />
work packages associated with<br />
‘Refits’. All this has required the<br />
development of a more dynamic<br />
relationship between ship and<br />
shore. The associated review of<br />
the Upkeep Cycle has<br />
recommended slightly more<br />
frequent, but shorter dockings –<br />
with an associated increase in<br />
availability to the extent that 9 of<br />
the 10 MCMVs are likely to be<br />
needed for current tasking levels.<br />
Under the previous regime all 10<br />
MCMVs would have been needed.<br />
The potential impact on support<br />
costs is clear if this were to be<br />
followed through to the logical<br />
conclusion.<br />
FIGURE 6: TYPE 23 FRIGATE<br />
Overall costs for running the RCM<br />
programme on Hunt amounted to<br />
£2M. Across the Class, savings<br />
of around £5M per annum are<br />
expected, providing a Return on<br />
Investment measured in months.<br />
The encouraging results of the<br />
Hunt Class trial were sufficient to<br />
harness support for an extensive<br />
programme to apply RCM-based<br />
maintenance regimes to a range<br />
of other platforms, a process<br />
which is now well and truly<br />
underway.<br />
Implementation to Type 23<br />
Frigate<br />
The RCM analysis and<br />
implementation on HMS<br />
Lancaster was completed in mid-<br />
2002, providing confidence that<br />
the RCM process can be applied<br />
to a major warship. Over 31,000<br />
failure modes had been<br />
examined over 377 separate<br />
systems with once again, a major<br />
shift towards condition-based<br />
maintenance with only 14% of<br />
failure modes responding to<br />
some form of scheduled<br />
restoration or discard (overhaul)<br />
activity. Benefits obtained so far<br />
include:<br />
• Removal of maintenance with no<br />
value;<br />
• Less overhaul and reduced<br />
requirement for docking when<br />
compared with the former<br />
maintenance cycle. Reduction in<br />
the time needed for maintenance<br />
is flowing through to shorter<br />
periods available for refit which in<br />
turn is forecast to improve<br />
contractor efficiency;