<strong>Forensic</strong> Consulting Services <strong>Report</strong><br />
Town of <strong>Trumbull</strong>, Connecticut<br />
Page 10<br />
The work was awarded to Mark <strong>IV</strong> and the contract was signed in May 2007. There were 21 change<br />
orders to the contract totaling $1,674,005 (11%). In addition, there were extensions of this contract<br />
totaling $3,500,000.<br />
The $3,500,000 extension (also know as the Jog Hill extension) did not go through a formal<br />
advertised bid process. The Town and <strong>WPCA</strong> had great difficulty in finding any documentation<br />
related to the $3,500,000 extension. The purchasing department stated that those estimates were<br />
provided by the Sewer Department and indicated that there were formal approvals by the <strong>WPCA</strong><br />
board (February 27, 2008), the Board of Finance (May 15, 2008) and the Town Council (June 2,<br />
2008). The Sewer Administrator did not have any formal calculation for the $3,500,000 other than<br />
stating to CCR/Beta in an e-mail correspondence “The method for determining the $3.5 million was<br />
nowhere to be found in the correspondence file. I remember that it was simply stated that the<br />
original 15 mile total and completed sum at the time the extension was proposed was approximately<br />
$17.4 million. It was estimated that the length of the 1 st extension including easements was<br />
approximately 3 miles. Thus, $17.4 million per mile divided by 15 miles equals $1.16 million per<br />
mile times 3 miles equals $3.48 million dollars. It may sound simplistic, but that is the way it was<br />
done.”<br />
It should be noted that the Town Charter does allow a waiver of some of the purchasing policies<br />
related to bids (see Exhibit A). The Charter states “bids may be waived after the purchasing<br />
authority has obtained written approval of the First Selectman in any case in which compliance with<br />
this subsection shall be deemed to be impractical or not in the best interest of the Town. The record<br />
of any purchase made pursuant to such a waiver shall include a copy of the waiver, which shall<br />
contain a statement of the reasons therefore, and shall be kept on file in the office of the purchasing<br />
authority where it shall be open to public inspection.” The Town Purchasing office was not able to<br />
produce a bid waiver for the $3,500,000 Jog Hill extension.<br />
Construction Related Bid / Award Process<br />
In late March of 2007 the Purchasing Agent for the Town of <strong>Trumbull</strong>, acting for and on behalf of<br />
the <strong>WPCA</strong> publicly advertised for construction bids for the proposed project entitled “Constructing<br />
Sanitary Sewers, <strong>Trumbull</strong> Connecticut, <strong>Phase</strong> 4, <strong>Part</strong> B, <strong>Contract</strong> 3” (hereinafter referred to as<br />
“<strong>Contract</strong> 3”). The established bid date was set for April 10, 2007 at 3:00 PM local time in the<br />
offices of the Town’s Purchasing Agent. At that time four sealed bids were received and publically<br />
opened by the Town. The bidding contractors, respective bid totals and ranking were as follows: