05.10.2014 Views

Forensic Audit Report-WPCA Phase IV, Part B. Contract ... - Trumbull

Forensic Audit Report-WPCA Phase IV, Part B. Contract ... - Trumbull

Forensic Audit Report-WPCA Phase IV, Part B. Contract ... - Trumbull

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Forensic</strong> Consulting Services <strong>Report</strong><br />

Town of <strong>Trumbull</strong>, Connecticut<br />

Page 25<br />

always installed as specified in all of the trenches prior to pavement being applied. Where<br />

suitable backfill material was found within the existing trench as determined by the Towns’<br />

onsite representative, it was substituted as an acceptable material for either the specified<br />

gravel base or the processed aggregate or both. Based on the lack of field records the number<br />

of times, the locations and the quantity of materials associated with this substitution is<br />

undocumented. Despite a clear reduction of work and material costs for the contractor there<br />

were no subsequent credits requested and/or received by the Town for allowing such a<br />

reduction by the contractor.<br />

‣ Although specified as a component of the Unit Price for “Temporary Pavement”, it was<br />

reported that although roadways were normally saw-cut prior to the excavation process, the<br />

limits of the trench were not typically re-cut and/or straightened back to the specified 1-foot<br />

minimum on either side of the trench or as typically desired, undisturbed and/or undamaged<br />

existing pavement. In addition the edges of existing pavement apparently were not<br />

vertically straightened, cleaned and painted with the specified liquid bitumen before paving<br />

as specified. As such the bonding between new and existing pavement is questionable.<br />

Despite a clear reduction of work and material costs for the contractor there were no<br />

subsequent credits requested and/or received by the Town for allowing such a reduction by<br />

the contractor.<br />

It should also be recognized that there are many conditions that impact the size/width of the<br />

overall trench receiving pavement restoration. These include items such as the following: the<br />

type, structural composition and condition of the roadways disturbed; the overall depth of the<br />

excavation along with the additional impacts resulting from any rock removal; any<br />

groundwater conditions encountered; the frequency and disturbances for perpendicular<br />

service connection cross trenches; and the mere magnitude of the construction operations on<br />

narrow residential streets. That being said it is fair to note many of <strong>Contract</strong> No. 3 roadways<br />

were most likely impacted far beyond the simplicity of being adequately repaired by<br />

applying a fairly narrow trench patch consistent with the designated pay width limits<br />

indicated under the contract (pipe diameter plus 6-feet). Consideration in terms of<br />

practicality, preserving a consistent pavement structure and the cost-effectiveness of having<br />

more reasonable pay limits based on various depths, should have been considered within the<br />

contract documents to provide the contractors more latitude during the bidding process<br />

thereby insuring adequate pavement restorations would be achieved.<br />

‣ Although the detail implies various pavement thicknesses would be encountered and, as a<br />

result restored by matching the actual depth of the existing pavement and paid for as a<br />

component of the Unit Price for “Temporary Pavement”, it was reported that the typical<br />

pavement thicknesses applied throughout the project area were limited to the specified 3-inch<br />

minimum. As such, in areas having thicker pavement depths the trench patches applied did<br />

not match or produce a uniformed pavement structure. Despite a clear reduction of work and<br />

material costs for the contractor on certain roadways, there were no subsequent credits<br />

requested and/or received by the Town for allowing such a reduction by the contractor.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!