05.10.2014 Views

Forensic Audit Report-WPCA Phase IV, Part B. Contract ... - Trumbull

Forensic Audit Report-WPCA Phase IV, Part B. Contract ... - Trumbull

Forensic Audit Report-WPCA Phase IV, Part B. Contract ... - Trumbull

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Forensic</strong> Consulting Services <strong>Report</strong><br />

Town of <strong>Trumbull</strong>, Connecticut<br />

Page 30<br />

Paragraph 2 of the General Conditions which states, “Prior to the first partial payment estimate the<br />

<strong>Contract</strong>or shall submit construction progress schedules showing the order in which he proposes to<br />

carry on the Work, including dates at which he will start the various parts of the Work, estimated<br />

date of completion of each part…” and Section 12 of the Supplemental General Conditions, which<br />

states “Prior to commencement of construction and within 10 days after the award of the <strong>Contract</strong><br />

the <strong>Contract</strong>or will be required to submit a detailed Sequence of Operations to the Engineer. This<br />

Sequence shall outline his exact construction schedule for the completion of the work embraced in<br />

this <strong>Contract</strong>”.<br />

Although it remains unclear as to whether or not these initial construction schedules were actually<br />

submitted (no records were provided), it is clear based on our interviews with the Town’s staff that<br />

updated schedules were not routinely requested by the Town nor provided by the contractor, and that<br />

any increases or decreases of the contractor’s onsite activities were made and accepted by the Town<br />

with little if any notice. Typically these notices were limited to the contractor’s verbal<br />

communications with the Town’s inspector a day or two before implementation.<br />

Reference is also made to the Division 9, Section 9.1 the fifth paragraph on Page 9.1-7/17 of the<br />

<strong>Contract</strong> Specifications, which specifically states “only one pipe-laying crew will be permitted to<br />

operate at any one time under one inspector” and further specifies that should the contractor wish to<br />

mobilized any additional crews “he must notify the Engineer at least two days in advance so that an<br />

adequate number of inspectors may be assigned to the job”. Certainly, this <strong>Contract</strong> provision fully<br />

expressed the Town’s intent to staff additional inspectors should the need arise. Unfortunately this<br />

did not occur and the level of inspection and the quality assurance monitoring of construction<br />

activities suffered as well as the ability to monitor quantities actually installed and maintain adequate<br />

field records.<br />

As stated above, despite their experience on prior Town contracts as well as this and current<br />

<strong>Contract</strong>s, when interviewed, the Town’s staff seemed to be uninformed and/or unfamiliar with the<br />

provisions of the <strong>Contract</strong> Documents at the time of actual construction, specifically the General<br />

Conditions, Supplemental General Conditions and Technical Specifications. Again, this failure to<br />

fully comprehend, understand and implement, or for that matter appreciate the provisions of the<br />

<strong>Contract</strong> Documents on all accounts appeared to open the door for leniency with such provisions and<br />

the quality assurances necessary to maintain administrative control of the project. In addition, in<br />

some cases, there may have been justifications for monetary credits due the Town if indeed elements<br />

of the <strong>Contract</strong> were not fully provided and/or performed by the <strong>Contract</strong>or.<br />

It is important to note, although it is the contractual responsibility of the contractor to fulfill his<br />

responsibilities of the <strong>Contract</strong>, it is also the responsibility of the Town, acting as the “Engineer”, to<br />

monitor the contractor’s compliance or noncompliance accordingly. Should items of noncompliance<br />

be found, it is the responsibility and obligation of the Town representatives to bring these issues to<br />

the attention of the <strong>Contract</strong>or, in written form if necessary, for immediate corrective actions. In the<br />

case of onsite field representatives providing inspection, any items of noncompliance should be duly<br />

noted in record form and reported to appropriate superiors along with a full description of the

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!