05.10.2014 Views

Forensic Audit Report-WPCA Phase IV, Part B. Contract ... - Trumbull

Forensic Audit Report-WPCA Phase IV, Part B. Contract ... - Trumbull

Forensic Audit Report-WPCA Phase IV, Part B. Contract ... - Trumbull

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Forensic</strong> Consulting Services <strong>Report</strong><br />

Town of <strong>Trumbull</strong>, Connecticut<br />

Page 12<br />

It appears construction bids were advertised, received and opened in accordance with the policies<br />

and procedures of the Town’s Purchasing Department, and in the proper sequence, timeframe and<br />

format typically found within the utility construction industry. Although there appears to be a wide<br />

variation of some unit prices between bidders, as well as the total cumulative amounts, no<br />

mathematical errors were found that would have altered either the dollar amounts bid or the overall<br />

ranking of the contractors bidding the project. Mark <strong>IV</strong> <strong>Contract</strong>ion’s total bid amount was indeed<br />

the lowest bid received. Reference is made to the attached “Bid Tabulation/Evaluation” attached to<br />

this <strong>Report</strong> as Exhibit E.<br />

There are however four primary items contained within Mark <strong>IV</strong> Construction’s bid that seems to<br />

have been the source for most (95%) of the $2.59 million difference between their low bid and that<br />

of the next lowest bid submitted by Guerrera Construction. These items include the following:<br />

Item Item Description Mark <strong>IV</strong> Guerrera Tabulated Bid<br />

No. Unit Price Unit Price Difference<br />

27 15-inch CPP Storm Drainage $1.00/LF $36/LF $ 802,935<br />

(0 to 10 foot depth)<br />

33 Trench Dam $0.01/EA $2,500/EA $ 50,000<br />

47 Trench Excavation – Rock $0.01/CY $34/CY $1,528,326<br />

(Assumed 7-ft Plus)<br />

51 Gutter-Milling of Existing $0.01/SY $2.25/SY $ 78,848<br />

Pavement<br />

Total Tabulated Bid Difference (of the above four items): $2,460,109<br />

It is difficult, if not impossible to ascertain a contractor’s overall bidding strategy, the manner in<br />

which he may prepare his bid, or the risks that he may or may not be willing to take in setting certain<br />

unit prices lower than expected. However, based on Mark <strong>IV</strong>’s prior history and experience of<br />

completing sewer related work within the Town, it is certainly a possibility that the company gained<br />

a bidding advantage knowing that certain items of work are not typically required or used in much<br />

lesser amounts, and thus lowering the his unit prices accordingly. Specific reference is made to Item<br />

Nos. 27, 33 and 51.<br />

In addition, there familiarity with the type of <strong>Contract</strong> Documents (both Design Drawings and<br />

Specifications) typically used by the Town and the manner and level of which they were interpreted<br />

and enforced by Town representatives, as well as a thorough examination of the actual documents<br />

being bid may have potentially opened the door of opportunity for gaining substantial increases to

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!