05.10.2014 Views

Forensic Audit Report-WPCA Phase IV, Part B. Contract ... - Trumbull

Forensic Audit Report-WPCA Phase IV, Part B. Contract ... - Trumbull

Forensic Audit Report-WPCA Phase IV, Part B. Contract ... - Trumbull

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Forensic</strong> Consulting Services <strong>Report</strong><br />

Town of <strong>Trumbull</strong>, Connecticut<br />

Page 26<br />

It should also be recognized that since there were no geotechnical investigations (i.e. borings,<br />

pavement cores, etc.) preformed and/or available for review during the bidding process for<br />

<strong>Contract</strong> 3, the contractors bidding the project had little or no documented assistance for<br />

anticipating pavement thicknesses. As a result it would be fair to say that the bidders most<br />

likely adjusted their prices accordingly to insure adequate compensation would be received<br />

should greater than minimum thicknesses were required. This along with the rather narrow<br />

pay limits for completing the trench restorations may account for the higher unit prices for<br />

Item No. 52.<br />

‣ In most cases, despite the lack of consistency with the above referenced detail, and therefore<br />

the contract requirements, it was reported that the “temporary pavement” placed during the<br />

initial trench paving operations was routinely accepted by the Town as the “permanent”<br />

pavement base as provided for and allowed under the provisions of Specification Section 4.3<br />

prior to application of the overlay surface course. As such, the Towns’ acceptance of a less<br />

than adequate “temporary” pavement as “permanent” may ultimately have been a major<br />

contributing factor to the significant amounts of “cracking” experienced in the overlay course<br />

on many project streets as reported and observed during site visits.<br />

“Permanent Pavement Overlay” Details<br />

The standard detail for “Permanent Pavement Overlay” delineated on Design Sheet D-1 indicates a<br />

6-foot wide gutter mill along the existing pavement edge (“as required by Town Engineer”) prior to<br />

the application of a full-width 1 ½-inch Class 2 wearing course. No gutter depths are indicated.<br />

Typically the purpose of a gutter mill is to reduce the thickness of the existing pavement thereby<br />

maintaining acceptable curb reveals and/or driveway matching once the overlay pavement course is<br />

applied. Gutter mills are also used as a means for establishing a cross-sectional crown to an existing<br />

roadway thereby shedding surface drainage towards the gutter.<br />

Based on our review, this element of the roadway restoration process was not used despite having<br />

such a specified provision, as well as a fairly attractive and established contractor unit price of $0.01<br />

per square yard. During interviews of Town representatives it was reported that the need for<br />

implementing the gutter milling process was not found necessary due to the existing condition of the<br />

roadways. In addition, it was stated that in many cases the gutter milling process was not used<br />

simply because of limited thicknesses of the existing pavement structure, thus any significant<br />

removal would have essentially removed most, if not all of the pavement base. It was also reported<br />

that the decision not to implement the gutter milling process was a general consensus between Town<br />

officials and the contractor based on the character of the existing roadways.<br />

“Gravel Access Drive” and “Grass Access Drive” Details<br />

Although both “Gravel Access Drive” and “Grass Access Drive” details were delineated on Design<br />

Sheet D-1 and were required as elements of the contract work for cross country applications, there<br />

were no pay items established within the original contract documents at the time of bid for the<br />

contractor to receive the appropriate compensation. The apparent lack of a designated Unit Price

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!