25.10.2014 Views

Melbourne–Brisbane Inland Rail Alignment Study - Australian Rail ...

Melbourne–Brisbane Inland Rail Alignment Study - Australian Rail ...

Melbourne–Brisbane Inland Rail Alignment Study - Australian Rail ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

7.3.3 Land acquisition<br />

A total of almost 600 km of greenfield alignments was<br />

identified where land acquisition would be required.<br />

Several factors were considered when estimating the<br />

valuation including value of land, severance, injurious<br />

affection, effects on irrigation systems, crop losses<br />

and disturbance.<br />

In addition to the estimates of compensation, other<br />

applicable land acquisition costs which would likely be<br />

incurred by an acquiring authority undertaking a land<br />

acquisition program of this nature were included. These<br />

included costs relating to land access and valuation,<br />

legal expenses and registration fees.<br />

Finally an estimate was made of total land division costs.<br />

These costs, which relate to transferring land ownership<br />

to the acquiring authority, include solicitors’ fees to<br />

facilitate contract and transfer documentation, plan<br />

registration fees, transfer registration fees, Crown land<br />

fees and stamp duty.<br />

7.3.4 Risk assessment<br />

A probabilistic risk estimate was developed to assess<br />

the financial impact of the various risks and opportunities<br />

associated with the proposed inland railway alignment.<br />

Box 7 below explains the risk estimation process.<br />

The risk estimate was based on the capital cost<br />

estimate for the railway together with an analysis<br />

of identified risks and opportunities. This bottom-up<br />

approach to risk estimation aimed to capture the<br />

breadth and detail of the project; it also enabled an<br />

accurate level of contingency for the project to be<br />

calculated in a transparent and methodical manner.<br />

Each element of the cost estimate was reviewed to<br />

determine the possible variability in the estimated most<br />

likely value. This variability was assigned to a program<br />

evaluation review technique (pert) distribution profile to<br />

calculate the range of costs.<br />

A risk register was developed and risk mitigation<br />

measures were considered. Residual risks were<br />

evaluated in terms of their likelihood, the minimum,<br />

maximum and most likely values.<br />

The risk model uses the variability and the residual risk<br />

values to calculate the capital cost estimate including<br />

the project risk contingency.<br />

7.3.5 Capital cost<br />

Capital cost estimates for the inland railway were<br />

produced using the estimated range in costs obtained<br />

from the risk assessment process described above.<br />

The P90 and P50 figures in the table below represent<br />

the probability that the actual cost can be achieved<br />

for these amounts or less. Their calculation is further<br />

explained in Box 7.<br />

The outturn capital cost for the Melbourne–Brisbane<br />

inland railway is contained in Table 17.<br />

Table 16 Summary of land acquisition costs (2010 dollars)<br />

Category Estimated cost ($)<br />

Land compensation estimate 239,125,000<br />

Additional land acquisition 32,090,000<br />

Consultants costs 21,696,000<br />

Total 292,911,000<br />

Table 17 Outturn capital cost (2010 dollars)<br />

Item Base estimate ($m) P50 estimate ($m) P90 estimate ($m)<br />

Capital construction cost 3,688.0 3,926.1 4,098.2<br />

Land acquisition cost 292.9 312.8 344.6<br />

Risk and opportunity allowance 181.1 258.5<br />

Total project cost 3,980.9 4,420.0 4,701.3<br />

54<br />

7. Delivery program and capital cost<br />

ARTC • Melbourne–Brisbane <strong>Inland</strong> <strong>Rail</strong> <strong>Alignment</strong> <strong>Study</strong> – Final Report

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!