MelbourneâBrisbane Inland Rail Alignment Study - Australian Rail ...
MelbourneâBrisbane Inland Rail Alignment Study - Australian Rail ...
MelbourneâBrisbane Inland Rail Alignment Study - Australian Rail ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
7.3.3 Land acquisition<br />
A total of almost 600 km of greenfield alignments was<br />
identified where land acquisition would be required.<br />
Several factors were considered when estimating the<br />
valuation including value of land, severance, injurious<br />
affection, effects on irrigation systems, crop losses<br />
and disturbance.<br />
In addition to the estimates of compensation, other<br />
applicable land acquisition costs which would likely be<br />
incurred by an acquiring authority undertaking a land<br />
acquisition program of this nature were included. These<br />
included costs relating to land access and valuation,<br />
legal expenses and registration fees.<br />
Finally an estimate was made of total land division costs.<br />
These costs, which relate to transferring land ownership<br />
to the acquiring authority, include solicitors’ fees to<br />
facilitate contract and transfer documentation, plan<br />
registration fees, transfer registration fees, Crown land<br />
fees and stamp duty.<br />
7.3.4 Risk assessment<br />
A probabilistic risk estimate was developed to assess<br />
the financial impact of the various risks and opportunities<br />
associated with the proposed inland railway alignment.<br />
Box 7 below explains the risk estimation process.<br />
The risk estimate was based on the capital cost<br />
estimate for the railway together with an analysis<br />
of identified risks and opportunities. This bottom-up<br />
approach to risk estimation aimed to capture the<br />
breadth and detail of the project; it also enabled an<br />
accurate level of contingency for the project to be<br />
calculated in a transparent and methodical manner.<br />
Each element of the cost estimate was reviewed to<br />
determine the possible variability in the estimated most<br />
likely value. This variability was assigned to a program<br />
evaluation review technique (pert) distribution profile to<br />
calculate the range of costs.<br />
A risk register was developed and risk mitigation<br />
measures were considered. Residual risks were<br />
evaluated in terms of their likelihood, the minimum,<br />
maximum and most likely values.<br />
The risk model uses the variability and the residual risk<br />
values to calculate the capital cost estimate including<br />
the project risk contingency.<br />
7.3.5 Capital cost<br />
Capital cost estimates for the inland railway were<br />
produced using the estimated range in costs obtained<br />
from the risk assessment process described above.<br />
The P90 and P50 figures in the table below represent<br />
the probability that the actual cost can be achieved<br />
for these amounts or less. Their calculation is further<br />
explained in Box 7.<br />
The outturn capital cost for the Melbourne–Brisbane<br />
inland railway is contained in Table 17.<br />
Table 16 Summary of land acquisition costs (2010 dollars)<br />
Category Estimated cost ($)<br />
Land compensation estimate 239,125,000<br />
Additional land acquisition 32,090,000<br />
Consultants costs 21,696,000<br />
Total 292,911,000<br />
Table 17 Outturn capital cost (2010 dollars)<br />
Item Base estimate ($m) P50 estimate ($m) P90 estimate ($m)<br />
Capital construction cost 3,688.0 3,926.1 4,098.2<br />
Land acquisition cost 292.9 312.8 344.6<br />
Risk and opportunity allowance 181.1 258.5<br />
Total project cost 3,980.9 4,420.0 4,701.3<br />
54<br />
7. Delivery program and capital cost<br />
ARTC • Melbourne–Brisbane <strong>Inland</strong> <strong>Rail</strong> <strong>Alignment</strong> <strong>Study</strong> – Final Report