CHAPTER 4<br />
JOB-<strong>MIX</strong> FORMULA<br />
4.1 General. The Contractor is responsible for the design of each job mix formula used<br />
on the project and for any necessary adjustments during production. A job mix<br />
formula may be a new design, or one being transferred from a previous project for<br />
which it was developed and under the conditions set out in the specifications. The<br />
Contractor shall not place any mixture prior to receiving a “tentative” approval for<br />
the job mix formula and a MDOT design number from the Central Laboratory.<br />
MDOT is responsible for the verification of each job mix formula submitted by the<br />
Contractor for use on the project.<br />
4.2 Contractor Responsibilities.<br />
4.2.1 Original Design of Job Mix <strong>For</strong>mula. Design the job mix formula in<br />
accordance with MT-78. At least 10 working days prior to the proposed use of each<br />
mixture, submit in writing to the Engineer (with a copy to the District Materials<br />
Laboratory) the proposed job mix formula signed by a CMDT Technician. Prepare<br />
samples of the materials representative of the job mix formula for submission to<br />
MDOT’s Central Laboratory in accordance with MT-78.<br />
4.2.2 Job Mix <strong>For</strong>mula Transfers. A verified job mix formula may be transferred<br />
from one project to another under the following conditions:<br />
If the mixture is currently being produced on the project from which it is being<br />
transferred, check the quality control test results and the quality assurance test<br />
results to verify consistent performance to the job mix tolerances. If the test<br />
results show satisfactory performance, the job mix formula may be transferred.<br />
A summary of the results on MDOT <strong>For</strong>ms TMD-006 and TMD-008 shall be<br />
provided along with information on which projects the job mix formula had<br />
previously been used.<br />
If the mixture is not currently being produced on an active project or has not<br />
been produced within the past six months, run the bulk specific gravity test on<br />
each aggregate component. If the specific gravity of each individual aggregate<br />
component is within a tolerance of ±0.025 from the original job mix formula,<br />
the combined bulk specific gravity of the aggregate blend is within a tolerance<br />
of ±0.015 from the original job mix formula, and the mixture properties meet<br />
the design requirements when calculated with the new aggregate specific<br />
gravity results, the job mix formula may be transferred.<br />
At least 10 working days prior to the proposed use of each mixture, submit in<br />
writing to the Engineer (with a copy to the District Materials Laboratory) a<br />
Rev. February 5, 2007 14