Deliver or have the Contractor deliver the samples required in MT-78 to the Central<br />
Laboratory.<br />
4.3.1.3 Central Laboratory. Check the Contractor’s job mix formula for accuracy<br />
and conformance to design characteristics required in the specifications for the<br />
required <strong>HMA</strong> mixture.<br />
Check to see if each coarse aggregate component is from an approved source. If not,<br />
check for sample(s) from the District Materials Laboratory for source approval. Test<br />
the sample(s) in accordance with AASHTO T 19, T 96 and T 104, and determine<br />
conformance to Section 703 of the Standard Specifications.<br />
Test Contractor samples submitted with the job mix formula, in accordance with<br />
current MDOT policy.<br />
If all test results are found to be in conformance with the specification requirements,<br />
issue the verified job-mix formula on <strong>For</strong>m TMD-042 by cover letter. If the mixture<br />
is found not to be in conformance with the specification requirements, reject the job<br />
mix formula with an explanation of the reasons for the rejection in writing.<br />
4.3.2 Job Mix <strong>For</strong>mula Transfers.<br />
4.3.2.1 Project Engineer. Determine if the original job mix formula complies with<br />
the bid items in the contract for which the transfer is to be made. If the request does<br />
not conform to the mixture type set out in the bid items, reject the request and return<br />
to the Contractor by cover letter explaining the reason for rejection. If the<br />
Contractor’s request is in conformance with the bid items, forward the request to the<br />
District Materials Engineer..<br />
4.3.2.2 District Materials Laboratory.<br />
Verification of the Contractor’s request for transfer of a job mix formula from one<br />
project to another will be based on the Contractor’s documentation, and such<br />
additional testing and investigation that may be necessary. Verify that the source<br />
and characteristics of the materials have not changed since the original job mix<br />
formula was issued. Perform any additional testing and investigation that may be<br />
necessary for verification.<br />
If it is determined that there has been a change in the source of any component<br />
material(s) or there has been a change in any characteristics of the material(s) or<br />
mixture, reject the Contractor’s request in writing giving the reasons for rejection.<br />
When the investigation confirms that the source and characteristics of materials has<br />
not changed, the requested transfer may be made. The District Materials Engineer<br />
must submit a written request for the transfer to the State Materials Engineer. This<br />
Rev. February 5, 2007 18