Benchmarking to...<br />

Continued from page 27<br />

using 20 foot-long shipping containers<br />

which can be stored outdoors during nonoutage<br />

periods.<br />

The result is noteworthy. A reduction<br />

of 18 days of total critical path savings<br />

NPTS, Inc.<br />

an Engineering, Design, and<br />

Construction <strong>Management</strong> firm has<br />

current and anticipated openings for<br />

the following positions:<br />

• Licensing, USAR & Regulatory<br />

Engineers<br />

• Engineering Design (All Disciplines)<br />

• Sr. Project Managers (All Disciplines)<br />

• Sr. Project Planners (All Disciplines)<br />

• Power Upgrade Project Engineers<br />

• Construction <strong>Management</strong>, Planners,<br />

Schedulers, Estimators<br />

• Resident Engineers (All Disciplines)<br />

• Operations Support Engineers<br />

• Operations Training Instructors<br />

• Procurement Specialists & Expeditors<br />

• Start-up & Commissioning Engineers<br />

For Power Uprates, New Builds, Life<br />

Extension, Upgrades, Modification and<br />

Maintenance Projects<br />

Please forward Resumes to:<br />

NPTS, Inc.<br />

2060 Sheridan Drive<br />

Buffalo, New York 14223<br />

Phone: 716.876.8066<br />

Fax: 716.876-8004<br />

E-mail: rbroman@npts.net<br />

for the Entergy fleet is realized across the<br />

three plants. Additionally, a safer work<br />

environment is created as it is designed<br />

to allow the addition of lead shielding for<br />

worker protection.<br />

Summary indicators for the three<br />

Entergy facilities, FitzPatrick, Pilgrim<br />

and Vermont Yankee are:<br />

• Total time saved: 18 days- 6 days per<br />

site- due to platform<br />

Additionally, a total of 720 hours of<br />

non- productive standby time for invessel<br />

inspectors was eliminated for<br />

the three stations<br />

• Total cost-savings: $10,869,120 Additional<br />

cost saving are realized by<br />

using the platform at each site<br />

ANO Seeks to be the<br />

Best<br />

After working at Entergy’s Arkansas<br />

<strong>Nuclear</strong> One Station in Russellville,<br />

Hoffpauir says of his current management<br />

role that he “misses seeing the<br />

people in the plant every day.” He knows<br />

of the dedication and team-work that the<br />

personnel at ANO display year-round and<br />

especially during an outage. Make that,<br />

record-breaking outages.<br />

Bob Pace, outage manager at ANO,<br />

thinks that a competitive spirit can be a<br />

healthy thing. ANO unit 1 set a personal<br />

best for a Babcock & Wilcox reactor<br />

at 22.5 days then bested that mark to a<br />

notable 21.2 days. The ANO unit 2 holds<br />

the Entergy PWR record at 20 days, 11<br />

hours for reactor outage duration.<br />

Ask Pace what makes the difference<br />

in performance and he answers quickly<br />

and credits the ANO staff. “ANO<br />

has an experienced workforce that is<br />

conscientious, loves working in the area<br />

and they have a strong work ethic across<br />

the board. I am constantly impressed with<br />

the people here,” Pace states.<br />

“I have had outstanding predecessors<br />

that have set high expectations and<br />

excellent processes in place,” notes Pace<br />

who has been in the current position<br />

nearly 2 years. The support of the Entergy<br />

fleet is of paramount importance. “We are<br />

supported by the entire fleet and couldn’t<br />

do it without them,” he says.<br />

Two other aspects stand-out as<br />

success factors for ANO. Pace noted<br />

that ANO has a high rate of workers<br />

that return year-after-year for outages.<br />

Historically, this minimizes the new-tonuclear<br />

staffing. “People love coming<br />

here to do the work. They understand the<br />

plant and the culture,” Pace adds.<br />

The second factor is that ANO is<br />

“very critical of our own performance.”<br />

Pace discussed how during systematic<br />

reviews, the staff is very critical and very<br />

detailed at uncovering emerging issues and<br />

overcoming challenges. Benchmarking to<br />

high standards is a part of the culture. He<br />

sees that as a plus for his site.<br />

Do they talk about records?<br />

“Absolutely. We see every outage as the<br />

next opportunity to be the best – in safety,<br />

in staffing, in outage performance,” Pace<br />

concluded.<br />

Contact: Margie Jepson, EquaGen,<br />

1340 Echelon Parkway, Jackson, MS<br />

39213; telephone: (601) 368-5460, email:<br />

mjepson@entergy.com.<br />

<br />