20.11.2014 Views

Nuclear Plant Journal Outage Management ... - Digital Versions

Nuclear Plant Journal Outage Management ... - Digital Versions

Nuclear Plant Journal Outage Management ... - Digital Versions

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Exelon, Continuum Dynamics,<br />

Inc. and Structural Integrity Associates<br />

identified MSL locations for 56 strain<br />

gages and 33 accelerometers. The<br />

instruments were strategically placed on<br />

the MSL as input to the acoustic circuit<br />

analysis for steam dryer loading and MSL<br />

vibration evaluations.<br />

In May 2005, Quad Cities unit 2<br />

ramped up in power based on the startup<br />

test plan and collected data from the<br />

sensors on the steam path at the designated<br />

power levels. Data acquisition equipment<br />

was obtained to collect steam dome, steam<br />

dryer and main steam line strain gage,<br />

pressure transducer and accelerometer<br />

data simultaneously. When a power level<br />

was reached, the data were collected and<br />

analyzed based on pre-established go<br />

/ no-go criteria until 2832 MWt; which<br />

was the highest MWt at EPU that could<br />

be reached with the environmental factors<br />

for that time of year.<br />

The data from the instrumented MSLs<br />

and steam dryer revealed the pressure<br />

oscillations at approximately 157 Hz<br />

that dramatically increased in amplitude<br />

above the original licensed thermal power.<br />

These high frequency pressure oscillations<br />

peaked on the dryer surface directly in<br />

front of the main steam line nozzles. This<br />

testing showed that the ERV and MSSV<br />

standpipes at Quad Cities were a probable<br />

cause of the increased loading on not only<br />

the dryer, but also on the entire steam<br />

path.<br />

In December 2005, an electrical<br />

ground was found present on the Quad<br />

Cities unit 2 3D ERV. The subsequent<br />

inspection revealed significant internal<br />

damage to the solenoid actuator. Additional<br />

inspections of the remaining ERVs<br />

for both Quad Cities units show significant<br />

wear and loose parts on the solenoid<br />

actuators. The root cause once again<br />

pointed to high frequency vibration damage.<br />

These valves are safety related components<br />

and are required to operate in the<br />

event of MSL over pressurization.<br />

The probable root cause identification<br />

and the additional ERV damage escalated<br />

the need for a MSL load reduction device.<br />

The starting point for this project was to<br />

assemble a team of industry experts to<br />

brainstorm possible mitigation devices.<br />

The ideas for mitigation ranged from<br />

making Quad Cities ERV and MSSV<br />

standpipes the same diameter as Dresden<br />

to changing the height of the standpipes<br />

as well as several other combinations of<br />

geometry changes.<br />

To ensure the various ideas were<br />

tested appropriately, the team determined<br />

a scale model test program that would be<br />

benchmarked against the in-vessel and<br />

steam path data collected at Quad Cities<br />

was required. To perform this successfully,<br />

the appropriate Reynolds Number<br />

had to be applied correctly throughout<br />

the test rig, otherwise the results would<br />

not reflect actual in-plant data. This presented<br />

a challenge since to achieve the<br />

appropriate Reynolds numbers, the scale<br />

model test had to be at elevated pressures,<br />

making the test rig at full scale very large.<br />

Continuum Dynamics, Inc. (CDI) was<br />

contracted to develop a pressurized test<br />

rig and perform the benchmark to Quad<br />

Cities in-plant data at subscale to avoid<br />

this problem.<br />

With this approach CDI was able to<br />

correctly duplicate the high frequency<br />

response from the Quad Cities main<br />

steam line actual in-plant data with the<br />

scale model test rig. This confirmed the<br />

probable root cause to be from the relief<br />

valve standpipes. Based on domestic and<br />

international benchmarking, this is an<br />

industry first, to take in-plant data from an<br />

instrumented steam path and successfully<br />

benchmark a scale model test rig against<br />

the data.<br />

With the benchmark completed,<br />

hundreds of tests were performed on<br />

numerous mitigation concepts, in addition<br />

to optimizing the acoustic side branch<br />

concept.<br />

In the end the team selected an<br />

acoustic mitigation device that branches<br />

off the valve standpipe side. This option<br />

was chosen for the following reasons:<br />

• The acoustic side branch (ASB)<br />

addition increases the effective length<br />

(L) of the standpipe, decreasing the<br />

acoustic standing wave frequency<br />

(f).<br />

• The vortex shedding frequency<br />

remains unchanged at the same<br />

power level, but the acoustic and<br />

vortex shedding frequencies are no<br />

longer coupled, so that resonance<br />

does not occur.<br />

• The acoustic frequency decrease<br />

lowers the velocity at which vortex<br />

shedding will excite the acoustic<br />

standing wave (i.e. the acoustic<br />

(Continued on page 40)<br />

<strong>Nuclear</strong> <strong>Plant</strong> <strong>Journal</strong>, May-June 2009 www.nuclearplantjournal.com 39

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!