TNB Financial Report 2002<br />

71 List of Properties TRANSMISSION<br />

Nature of LAND BUILDINGS DESCRIPTION<br />

Functional<br />

Activity Leasehold Freehold Total Total Total Built-Up NBV<br />

No. of Area NBV No. Area (RM’000)<br />

TRANSMISSION No. of Area NBV No. of Area NBV Lots (sq M) (RM’000) (sq M)<br />

Lots (sq M) (RM’000) Lots (sq M) (RM’000)<br />

Location (1) (2) (3) (4) (5) (6) (1+4) (2+5) (3+6) (10) (11) (12) (13)<br />

Perlis 4 110,024 1,140 2 15,860 474 6 125,884 1,614 8 3,145 17,967 Main Intake<br />

Kedah 12 445,892 3,845 7 47,652 36,262 19 493,544 40,107 34 7,694 154,248 Substations<br />

Pulau Pinang 15 1,313,551 5,881 7 112,804 7,144 22 1,426,355 13,025 16 2,923 103,716<br />

Perak 10 157,193 1,658 7 26,438 10,486 17 183,631 12,144 28 7,405 191,105<br />

Selangor 15 205,182 22,435 24 80,952 33,448 39 286,134 55,883 58 13,218 392,059<br />

W. Persekutuan 10 176,794 12,165 10 79,800 12,114 20 256,594 24,279 18 7,740 302,458<br />

N. Sembilan 13 688,904 7,418 10 87,029 1,153 23 775,933 8,571 29 3,836 70,939<br />

Melaka 6 59,717 1,473 15 20,627 12,404 21 80,344 13,877 24 7,167 75,793<br />

Johor 30 570,739 12,994 30 48,335 14,698 60 619,074 27,692 50 8,807 607,016<br />

Pahang 9 97,021 1,255 17 160,085 4,069 26 257,106 5,324 21 2,934 112,142<br />

Terengganu 4 170,622 3,546 – – – 4 170,622 3,546 19 3,544 44,819<br />

Kelantan 3 95,628 2,034 4 176,029 1,470 7 271,657 3,504 18 5,551 43,966<br />

Sabah 3 30,904 2,056 1 14,165 134 4 45,069 2,190 7 3,600 3,925<br />

TOTAL 134 4,122,171 77,900 134 869,776 133,856 268 4,991,947 211,756 330 77,564 2,120,153<br />

Note:<br />

TRANSMISSION<br />

Transmission activity relates to the process of transmitting electricity generated at power stations to the load centres where it is required, eg. townships, industrial growth centres and major<br />

Customers. A network of transmission lines, forming the National Grid is required for this purpose. At appropriate sites, transmission substations are constructed to channel electricity from the<br />

National Grid to the numerous load centres. The transmission system operates at voltage levels of 500 kV, 275kV, 132kV and 66kV.<br />