Dy.CSTE/Con/ IZN/02 of 2011 <strong>North</strong> <strong>Eastern</strong> <strong>Railway</strong><br />

All care should be taken in handling cable drums with a view to ensure safety not of<br />

the cables but also of the working party handling them. The man should not be allowed to<br />

brake the cable drum by standing in front but only from side.<br />

3.11. REWINDING AND REDRUMING <strong>OF</strong> CABLES.<br />

i) If for any reason it is found necessary to rewind a cable on a drum, cable drum<br />

with a proper barrel diameter not less than of the original drum should be<br />

chosen.<br />

ii) The drums should be mounted on cable jacks during rewinding operations<br />

using proper size of spindles passed through the flange holes which will<br />

not buckle under the lead. The cable should not be bent opposite to the set it is<br />

having already.<br />

iii) In the redruming operations the full and empty drums should be so turned that<br />

the cable passes from the bottom of the original set as little as possible\<br />

iv) Replace all the laggings on the cable drum.<br />

3.12 CABLE LAYING:<br />

3.12.1 It is advisable to employ the same people at the same place or job while cable is being<br />

laid.<br />

3.12.2 Before commencement of the laying inspection of the trench and inspection of<br />

protection works should be carried out so as to ensure their conformity with the<br />

specification. The trench bottom should be clean, smooth and free of small stone.<br />

When the soil contains stone or pieces of rock and therefore cannot be raddled, sieved<br />

earth about 10 cm thick should be used both for the bedding on which the cable is<br />

laid and for covering the cables.<br />

3.12.3 The cable drum should be brought as close to the cable trench as possible. it should be<br />

lifted with the aid of cable jacks firmly mounted on a support of stone or wood . The<br />

spindle should be minimum of 55mm diameter and lower edge of drum should be 5 to<br />

10 cm above the ground.<br />

3.12.4 Where necessary the cable drum may be placed at such a point so that 2/3 of the cable<br />

is laid directly and the balance in other direction. Care should be taken in such a case<br />

to see that there is no kinks or loops in the cable.<br />

3.12.5 The wooden battens on the drums should be carefully removed shortly prior to laying<br />

and before the drum is mounted on the jack. The nails on the lagging should be<br />

carefully removed.<br />

3.12.6 While rolling a cable drum for laying the drum shall be supported on an axle running<br />

through its center the height of the axle being such that the end frames are free to<br />

rotate and do not touch the ground at any point. The cable shall be carefully uncoiled<br />

by gently pulling the cable assisted as necessary by carefully turning the drums quick<br />

pulling of the cable or turning the drums shall be avoided at all costs. Each cable drum<br />

shall be braked while laying is in progress to prevent sharp bending or buckling,<br />

particularly when the cable coils are sticking together.<br />

3.12.7 The following personnel shall be employed near the drum.<br />

1 Man : for handling the brakes.<br />

1 Man : for permanent observation of the uncoiling of cable.<br />