22.04.2015 Views

Report - Fire Brigades Union

Report - Fire Brigades Union

Report - Fire Brigades Union

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

SECTION B — FIRE AND RESCUE SERVICE POLICY<br />

<strong>Fire</strong>link/FiReControl<br />

76) The original timetable to complete FiReControl by<br />

December 2007 was tied to the completion of <strong>Fire</strong>link, the<br />

new digital radio system, which had a delayed completion<br />

date of December 2007. <strong>Fire</strong>link is providing the vast<br />

majority of the benefits claimed for RCCs and is very<br />

technically challenging in its own right.<br />

77) While we know <strong>Fire</strong>link radio technology can work for<br />

brigade level controls there has to be a question mark over<br />

its capacity to work across several fire services regionwide.<br />

There are already genuine question marks about the<br />

capacity of Airwave, which is now a private monopoly<br />

supplier to the emergency services, given the increasing<br />

burdens being placed on it.<br />

78) Delays to <strong>Fire</strong>link do have a knock-on effect on<br />

FiReControl. Some of these were set out in a national<br />

project manager’s update, <strong>Fire</strong>link Strategic Snapshot –<br />

December 2007. This acknowledged that a number of fire<br />

services did not update their existing controls – known as<br />

legacy systems – because the new RCCs were meant to<br />

be in place by the end of 2007.<br />

79) Delays to both the <strong>Fire</strong>link and FiReControl projects meant<br />

“interim solutions” had to be put in place to cope with the<br />

late-running of both projects. Additional work had to be<br />

carried out for what was described as the “longer<br />

extended interim solution”.<br />

80) Problems identified in the <strong>Fire</strong>link Phase A operational<br />

rollout included: Fit out of eight pilot vehicles in each FRS:<br />

“temporarily stalled in the first tranche of regions due to<br />

delays by Airwave in providing test scripts.” Issues with<br />

training “eg lack of training equipment.”<br />

81) Problems were identified in the Phase B launch date<br />

(the fit out of the main vehicle fleets). This was<br />

“progressively delayed as a result of… over ambitious<br />

forecasting and inadequate groundwork by Airwave…<br />

delays in submission of test scripts for Phase A<br />

acceptance work… knock-on effects of the (preceding)<br />

police resilience programme.”<br />

82) These issues meant “Airwave roll out forecasts have been<br />

drifting increasingly out of synchronisation with events on<br />

the ground since the late summer”. The result was a<br />

“realism adjustment” – a euphemism for a further delay.<br />

<strong>Fire</strong>link project managers reported they had been able “to<br />

persuade Airwave fully to reflect the reality of where we<br />

are and their track record to date by adding a significant<br />

amount of contingency to their forecasting.”<br />

83) This strategic snapshot is also revealing in a number of<br />

other points. Concerns about the fitting of aerials to<br />

officers’ cars threw up other concerns about “the evolving<br />

FiReControl concept of operations appears now to be<br />

shifting beyond the current <strong>Fire</strong>link scope of supply based<br />

on a wider interpretation of the term ‘resilience’. Separate<br />

work is therefore now in hand… to clarify the FiReControl<br />

concept of operations…”<br />

84) The concept of operations would play a major role in<br />

setting out the technical specifications for the contract<br />

agreed with EADS. That it was still evolving at this stage –<br />

there was still no fixed concept of operations – would<br />

make it much more difficult to establish the technical<br />

solution.<br />

85) The same report includes part of a letter from Richard<br />

How, the senior civil servant heading up the FiReControl<br />

project on a day to day basis. This letter, to the <strong>Fire</strong>link<br />

team, reveals there were already concerns about delays for<br />

FiReControl arising a matter of months after EADS secured<br />

the contract.<br />

86) It revealed that Mr How had written to the <strong>Fire</strong>link team at<br />

the end of August 2007 about “concerns that the release<br />

dates for a number of products – in particular Convergence<br />

and Data Schema – from EADS were later than planned.”<br />

Mr How told the <strong>Fire</strong>link team, operating from within the<br />

same department and upon which FiReControl depended,<br />

that EADS provided some information but that it would “be<br />

counter-productive” to share that with them at that time.<br />

87) By November Mr How could still not share the information.<br />

He could say that “Since then we have been working<br />

closely with EADS to develop a comprehensive set of<br />

robust plans in which we all have confidence… However,<br />

EADS is not as far advanced as they and we hoped they<br />

would be… this lack of information is preventing the FRS<br />

from developing their detailed activity and resources<br />

plans… the failure to deliver to date is inevitably creating<br />

concerns about the capability to deliver as they have<br />

contracted… the delay in providing information is<br />

compressing the time available that that (sic) the FRSs<br />

have to complete their activities…”<br />

88) It would be unfair to Airwave and EADS not to point out<br />

that these documents only set out the views of CLG<br />

project managers. These comments may be unfair to one<br />

or both contractors, may not fully set out the full picture or<br />

be self-serving in other ways.<br />

89) What is clear is the department was not ensuring the<br />

proper flow of full information between the key personnel<br />

and the key contractors working on two closely related<br />

projects. If anything, the department was a barrier to the<br />

flow of critical information between and within both<br />

projects.<br />

Overview – getting it wrong from the start<br />

90) The project is defined to operate under the Prince 2 project<br />

management process. Like all project management<br />

processes these define tasks, timelines, costs,<br />

checkpoints/gateways, actions, personnel, risks and should<br />

include for contingencies. The documented hierarchy<br />

published in the Business Cases (Part 1 and Part 2)<br />

provides for the accountability.<br />

91) The published delays do not account for the difference in<br />

time from the original proposal and the current end date.<br />

There must therefore have been significant delays during<br />

FBU Annual <strong>Report</strong> 2011 69

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!