22.04.2015 Views

Report - Fire Brigades Union

Report - Fire Brigades Union

Report - Fire Brigades Union

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

SECTION B — FIRE AND RESCUE SERVICE POLICY<br />

110)It is an oft-quoted comment from government that critics<br />

of the project are not comparing like with like, or using<br />

different timescales. The government appears to do this<br />

itself, making it very difficult to tie down what the full costs<br />

are or even details how the costings have changed in the<br />

various Business Cases.<br />

111)Differing language is used by government to describe<br />

various costs as “basic initial costs”, or “set up” costs to<br />

“estimated full cost of implementing FiReControl”. The<br />

Business Cases quote a figure of around £1.4billion,<br />

although that does include on-going staffing costs through<br />

the life of the project.<br />

112)These are included by government – it is their Business<br />

Case - because alleged savings were always based on<br />

cutting the numbers of emergency fire control staff. We<br />

will return to that issue later.<br />

On 22 October 2009 the following question was asked and<br />

answered:<br />

Mrs Spelman: To ask the Secretary of State for<br />

Communities and Local Government what recent estimate<br />

he has made of the total cost of delivery of the FiReControl<br />

project; and what estimates were made in (a) 2004, (b)<br />

2005, (c) 2006, (d) 2007 and (e) 2008. [293319]<br />

Mr Malik: The current estimated overall cost of delivery of<br />

the FiReControl project for (a) 2004 was £120 million; (b)<br />

2005 – £160 million; (c) 2006 – £190 million; (d) 2007 –<br />

£360 million; and (e) 2008 – £380 million.<br />

On 2 November 2009 Mr Malik answered in another<br />

question:<br />

The basic initial costs and timescales of implementing the<br />

FiReControl project, as originally estimated in 2004, were<br />

£120 million. Following more detailed work, project costs<br />

were updated to include funding to fire and rescue<br />

authorities for local and regional implementation activity,<br />

the costs of the regional control centre building leases and<br />

the costs of equipment to be installed in every fire station<br />

in England to support improved mobilisation.<br />

The expenditure to date on the project is approximately<br />

£190 million. The estimated full cost of implementing<br />

FiReControl is £420 million.<br />

113)Even on these figures the cost of the project has more<br />

than tripled.<br />

Why have costs increased?<br />

114)The reasons given in Mr Malik’s reply for some of the<br />

increased costs show how ill-thought the original estimates<br />

were. Mott MacDonald’s building costs estimates were<br />

£25.2 million and even over a ten year period (as opposed<br />

to the longer leases) are well short of the reality of the<br />

leasehold and other costs relating to the buildings.<br />

115)The fact that Station End Equipment – the ‘cost of<br />

equipment to be installed in every fire station’ – were left<br />

out of the calculations – beggars belief. It meant the<br />

project was moving along on the basis they had worked<br />

out the cost of the equipment needed to send a message,<br />

but not the fact there would need to be equipment to<br />

receive the message and it would have to be paid for.<br />

116)In a letter dated 13 November, in response to concerns<br />

raised by a constituent of Rob Marris MP, Mr Malik goes<br />

further in explaining the cost and time overruns: “the<br />

FiReControl technical solution has proved to be more<br />

complex than originally anticipated, and the development<br />

stages have taken much longer than expected.” He<br />

asserted that the contract with EADS was signed with<br />

them having a full “understanding of the technical solution<br />

required… [nor having full] information about the amount of<br />

work that would need to be carried out by the individual 46<br />

fire and rescue authorities”.<br />

117)Only once the contract had been signed – which was in<br />

2007 – he asserted, did “it become apparent that the<br />

project scope needed to be broadened”. No details of the<br />

broadening of the scope are given.<br />

118)The Outline Business Case (OBC) November 2004 sets out<br />

in some detail (at Appendix C) why the costings in the<br />

original Mott MacDonald report were wrong. The OBC<br />

identified some key areas of risks the project would face<br />

including that there was a very high risk of total project<br />

failure.<br />

119)The OBC uses a Private Developer Scheme (PDS) as its<br />

recommended method of supplying new Regional Control<br />

Centre buildings. It is an expensive option and the OBC<br />

underlines the catastrophic impact on any estimated<br />

savings of the buildings being completed more than six<br />

months before they are meant to become operational.<br />

120)The OBC heavily flagged up, as a significant risk, the<br />

financial impact of the buildings being completed more<br />

than six months before they were to start becoming<br />

operational. It also pointed out the importance of there<br />

being a degree of co-terminosity for leases for the new<br />

RCC buildings which would become the national network<br />

of regional control centres. That is they would all expire<br />

and have to be renewed at approximately the same time or<br />

within a reasonable period of each other.<br />

121)The OBC identified that from the signing of the PDS<br />

contracts to building completion would take around 18<br />

months. Building in a six month rent-free period from<br />

practical completion to becoming operational would deal<br />

with the issue of rents being paid for empty buildings and<br />

is a sensible recommendation.<br />

122)Having identified these two key traps to be avoided – and<br />

the mitigating steps needed to be taken to avoid them –<br />

the CLG project managers then walked into both traps. On<br />

10 August 2005, without any further Business Case of any<br />

kind, CLG announced it was proceeding with the PDS<br />

scheme, sites had been identified and the contracts signed<br />

with the developers for between 20 years and 25 years<br />

and which come to an end between 2027 and 2033.<br />

123)The minister, asked on 16 December in a parliamentary<br />

FBU Annual <strong>Report</strong> 2011 71

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!