28<br />

ITB 5.3<br />

The information required from bidders in ITB Sub-Clause 5.3 is modified as follows: “none”<br />

ITB 5.3 (j) The ceiling for sub contractor's participation is: 25%<br />

ITB 5.4<br />

ITB 5.5<br />

The qualification data required from bidders in ITB Sub-Clause 5.4 are modified as follows:<br />

“none”.<br />

The previous financial years are:<br />

2011-2012, 2010-2011, 2009-2010, 2008-2009, 2007-2008.<br />

ITB 5.5<br />

The qualification criteria in ITB Sub-Clause 5.5 are modified as follows:-<br />

_“none ________<br />

ITB 5.5 (A)<br />

(a) Financial turnover 9 : not less than Rs. 410.06 Millions<br />

(b) Completion of similar work of value of Rs 328.05 Millions. Water Supply works<br />

comprising of ELSRs , Gravity/ Pumping mains and Distribution lines will be<br />

considered as similar<br />

(c) Execution of minimum quantities of major components of work in any one year.<br />

Supply, Delivery and laying of HDPE Pipelines of OD 110<br />

mm and above.<br />

Supply, Delivery and laying of DI Pipelines of minimum<br />

Dia 350 mm.<br />

Construction of Elevated Service Reservoirs- 400 KL and<br />

above capacity<br />

123 Km<br />

1.9 km<br />

1 No.