22.11.2012 Views

Victorian Desalination Project - AquaSure

Victorian Desalination Project - AquaSure

Victorian Desalination Project - AquaSure

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

4 Commissioning Delivery Approach<br />

4.1 <strong>Project</strong> Delivery Mode and Contractual Requirements<br />

Commissioning Environmental Sub-plan (CESP)<br />

The State has contracted <strong>AquaSure</strong> to deliver the <strong>Project</strong>. As such, from 1 September 2009, the official<br />

status of <strong>Project</strong> proponent has been transferred from the State to <strong>AquaSure</strong>. The environmental<br />

requirements are set out in the <strong>Project</strong> Deed between <strong>AquaSure</strong> and the State. Clause 58.3 of the <strong>Project</strong><br />

Deed permits <strong>AquaSure</strong> to subcontract its obligations to the D&C Contractor.<br />

<strong>AquaSure</strong> has contracted TDJV to design, construct and commission the <strong>Project</strong> as its D&C Contractor.<br />

The relevant environmental requirements in the <strong>Project</strong> Deed have been transferred to TDJV via the D&C<br />

Contract between <strong>AquaSure</strong> and TDJV, although it should be noted that <strong>AquaSure</strong> is still required to meet<br />

all legislative requirements and has an obligation to ensure appropriate environmental management is<br />

implemented.<br />

TDJV has contractual responsibilities and obligations with a number of organisations to facilitate delivery of<br />

the <strong>Project</strong>.<br />

4.2 <strong>Project</strong> Phases<br />

The D&C component of the <strong>Project</strong> has the following phases:<br />

• Design and pre-construction<br />

• Construction<br />

• Commissioning<br />

• Close-out<br />

• Defects liability<br />

Key features implemented during the Design and pre-construction, and Construction phases of the D&C<br />

component include, but are not limited to:<br />

• Bunding of chemical storage areas<br />

• Construction testing and verification<br />

• Pre-Commissioning cleaning, verification and calibration.<br />

TDJV’s approach to environmental management during the Commissioning Phase is set out below:<br />

• The Commissioning and Commercial Acceptance Plan has been developed which establishes a<br />

high level framework for environmental management during commissioning activities.<br />

• Environmental risks associated with commissioning equipment failure and design and construction<br />

errors are identified and managed.<br />

• Specific environmental risks associated with commissioning are identified and addressed.<br />

• Changeover of environmental roles, responsibilities and accountabilities from the D&C Contractor<br />

to the O&M Contractor is managed effectively.<br />

// Page 23<br />

// TDV-0-EV-SB-0021.I-03

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!