Victorian Desalination Project - AquaSure
Victorian Desalination Project - AquaSure
Victorian Desalination Project - AquaSure
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
4 Commissioning Delivery Approach<br />
4.1 <strong>Project</strong> Delivery Mode and Contractual Requirements<br />
Commissioning Environmental Sub-plan (CESP)<br />
The State has contracted <strong>AquaSure</strong> to deliver the <strong>Project</strong>. As such, from 1 September 2009, the official<br />
status of <strong>Project</strong> proponent has been transferred from the State to <strong>AquaSure</strong>. The environmental<br />
requirements are set out in the <strong>Project</strong> Deed between <strong>AquaSure</strong> and the State. Clause 58.3 of the <strong>Project</strong><br />
Deed permits <strong>AquaSure</strong> to subcontract its obligations to the D&C Contractor.<br />
<strong>AquaSure</strong> has contracted TDJV to design, construct and commission the <strong>Project</strong> as its D&C Contractor.<br />
The relevant environmental requirements in the <strong>Project</strong> Deed have been transferred to TDJV via the D&C<br />
Contract between <strong>AquaSure</strong> and TDJV, although it should be noted that <strong>AquaSure</strong> is still required to meet<br />
all legislative requirements and has an obligation to ensure appropriate environmental management is<br />
implemented.<br />
TDJV has contractual responsibilities and obligations with a number of organisations to facilitate delivery of<br />
the <strong>Project</strong>.<br />
4.2 <strong>Project</strong> Phases<br />
The D&C component of the <strong>Project</strong> has the following phases:<br />
• Design and pre-construction<br />
• Construction<br />
• Commissioning<br />
• Close-out<br />
• Defects liability<br />
Key features implemented during the Design and pre-construction, and Construction phases of the D&C<br />
component include, but are not limited to:<br />
• Bunding of chemical storage areas<br />
• Construction testing and verification<br />
• Pre-Commissioning cleaning, verification and calibration.<br />
TDJV’s approach to environmental management during the Commissioning Phase is set out below:<br />
• The Commissioning and Commercial Acceptance Plan has been developed which establishes a<br />
high level framework for environmental management during commissioning activities.<br />
• Environmental risks associated with commissioning equipment failure and design and construction<br />
errors are identified and managed.<br />
• Specific environmental risks associated with commissioning are identified and addressed.<br />
• Changeover of environmental roles, responsibilities and accountabilities from the D&C Contractor<br />
to the O&M Contractor is managed effectively.<br />
// Page 23<br />
// TDV-0-EV-SB-0021.I-03