10.5 Audits<br />
10.5.1 <strong>AquaSure</strong><br />
TDJV will facilitate audits by the <strong>AquaSure</strong> EMR.<br />
Commissioning Environmental Sub-plan (CESP)<br />
The Commissioning Director, Commissioning Manager, Environmental Manager or Area Environmental<br />
Managers will respond to audit reports of the CESP received from the <strong>AquaSure</strong> EMR within the time<br />
specified by the EMR. TDJV will formulate a plan of action to follow-up the findings and recommendations<br />
of the audit, including:<br />
• Describing the planned corrective action/s for each finding<br />
• Nominating a time frame to complete the corrective actions<br />
• Nominating the responsible persons to carry out the corrective actions.:<br />
• Implement remedial/corrective actions within the agreed timeframes<br />
• Notify the EMR of close-out<br />
• Provide evidence of completion where agreed.<br />
The <strong>AquaSure</strong> EMR will review the close out of the audit findings.<br />
10.5.2 TDJV<br />
Internal environmental audits will be conducted in accordance with the MIRA Schedule (Attachment I.3)<br />
and to the standards described in the ‘Environmental Audits’ procedure attached to the EMS Manual.<br />
If the <strong>AquaSure</strong> EMR conducts an audit on an EMS component, that is also scheduled to be audited by<br />
TDJV, the EMR’s audit may suffice as the TDJV audit, with the consent of the EMR. As a guide, the<br />
<strong>AquaSure</strong> EMR and Environmental Manager will (separately or together) undertake the following types of<br />
audits on a regular basis (minimum quarterly):<br />
• D&C EMP - the scope of the audit will assess the level of implementation of the D&C EMP and the<br />
CESP through document review and on-site assessment<br />
• High Risk Activities- the scope of these audits will include an audit focussing on high risk<br />
activities to ensure that environmental controls and procedures outlined in the D&C and AEMPs<br />
are being implemented<br />
Non-conformances will be recorded and managed as set out in Section 9.<br />
10.5.3 External<br />
The IR&EA or the State may audit any part of the <strong>Project</strong> or EMS Manual or other environmental<br />
documentation with reasonable notice for the purposes of confirming compliance with <strong>Project</strong><br />
environmental PRs.<br />
TDJV will facilitate audits by other parties, including the IR&EA and the State as set out in Section 9.5.3 of<br />
the D&C EMP.<br />