22.11.2012 Views

Victorian Desalination Project - AquaSure

Victorian Desalination Project - AquaSure

Victorian Desalination Project - AquaSure

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

6.2.2 Attachment I.2 – Commissioning Management Strategies<br />

Commissioning Environmental Sub-plan (CESP)<br />

For the purpose of this CESP, commissioning involves the sequential and cumulative commissioning of<br />

several elements of the Desalinated Water Supply System, as set out in Figure 3 (Section 3.2<br />

Commissioning Components). A Commissioning Management Strategy for each of these elements is<br />

included within this Sub-plan. Each of these Commissioning Management Strategies is a procedural and<br />

practical document that clearly sets out the strategy for the commissioning of each component, including<br />

the environmental risks that are unique to the commissioning process and the measures to control these<br />

risks. Contingency risks and associated contingency control measures are also addressed within CESP<br />

Attachment I.2. The relevant contingency risks are similar to those outlined in the D&C PGA Risk Register,<br />

however contingency risks that are unique to Design and Construction are not covered within this CESP<br />

and will continue to be managed through the D&C EMP.<br />

6.2.3 Attachment I.3 – Monitoring, Inspection, Reporting and Auditing Schedule<br />

Environmental monitoring will be conducted in accordance with the Monitoring, Inspection, Reporting and<br />

Audit Schedule (MIRA Schedule). More information on monitoring and reporting is included in Section 10.<br />

6.2.4 Attachment I.4 – Commissioning Monitoring Program, interfacing with the Baseline<br />

Marine Monitoring Program (BMMP)<br />

The Commissioning Monitoring Program includes the following monitoring programs:<br />

• Baseline Marine Monitoring Program (BMMP) - This program comprises two components:<br />

• Coastal Processes Monitoring: impact monitoring commences at intake of seawater.<br />

Intake of seawater commences with the Marine Tunnels and Sea Water Lift Pump Station<br />

• Marine Ecosystems Monitoring: Impact monitoring commences with intake of seawater<br />

(inshore components) and discharge of brine (offshore components). Brine is first<br />

discharged during Overall Systems Commissioning.<br />

• Section 8 of the Section 30A Commissioning Approval Application which includes In-Plant Water<br />

Quality Monitoring and Diffuser Performance Monitoring.<br />

• Section 9 of the Section 30A Commissioning Approval Application which includes the following<br />

Tests and Assessments: Tracer Testing and Diffuser Validation, Direct Toxicity Assessment,<br />

Waste Characterisation, Odour Assessment and a site wide Noise Assessment.<br />

6.2.5 Attachment I.5 – Monthly Environmental Checklist<br />

Inspection requirements are set out in the MIRA Schedule (Attachment I.3). Any actions required, or<br />

measures determined not to be effective, will be identified on the Monthly Environmental Checklist, which<br />

facilitates the auditing process.<br />

6.3 Authorisation and Distribution<br />

Without limiting TDJV’s obligation to notify any proposed revisions or amendments to the D&C EMP and<br />

the Commissioning Sub-plan to <strong>AquaSure</strong>, the State and the IR&EA and TDJV overall responsibility for the<br />

D&C EMP, revisions or amendments to this CESP are subject to the authorisation process set out in the<br />

tables below.<br />

Table 6-2: CESP authorisation<br />

// Page 37<br />

// TDV-0-EV-SB-0021.I-03

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!