Commissioning Environmental Sub-plan (CESP)<br />

6 Commissioning Environmental Management Documentation<br />

6.1 Overview<br />

The CESP relates to the D&C EMP as set out in below. Details on the attachments for this CESP and<br />

where to find them are set out in Table 6-1 and Section 6.2.<br />

Attachments<br />

Plant &<br />

General Area<br />

EMP<br />

Attachments<br />

and Sub-<br />

Plans<br />

Attachment I.1<br />

Risk Register<br />

D&C EMP<br />

Attachment I.2<br />

Commissioning<br />

Management Strategies<br />

Attachment I.3<br />

Monitoring, Inspection,<br />

Reporting and Auditing<br />

Attachment I.4<br />

Commissioning<br />

Monitoring Program,<br />

interfacing with the<br />

BMMP and OMMP<br />

Attachment I.5<br />

Monthly Environmental<br />

Checklist<br />

Marine EMP Utilities EMP<br />

Attachments<br />

and Sub-<br />

Plans<br />

Attachments<br />

and Sub-<br />

Plans<br />

D&C Commissioning<br />

Environmental Sub-Plan<br />

Attachment I.2.1<br />

Marine Tunnels and Sea Water Lift<br />

Pump Station Commissioning<br />

Management Strategy<br />

Attachment I.2.2<br />

Pre-Treatment Commissioning<br />

Management Strategy<br />

Attachment I.2.3<br />

Reverse Osmosis and Potabalisation<br />

Commissioning Management Strategy<br />

Attachment I.2.4<br />

Overall Systems Commissioning<br />

Management Strategy<br />

Attachment I.2.5<br />

Commissioning Control Measures<br />

Table<br />

BMMP<br />

OMMP<br />

Figure 7 - CESP Document Structure<br />

O&M EMP<br />

Attachments<br />

Environmental Noise Assessment<br />

(COMM 051).<br />

Commissioning Procedure for Odour<br />

Assessment<br />

(COMM 052).<br />

Tracer Testing (Difuser Validation)<br />

and Direct Toxicity Assessment<br />

(COMM 053).<br />

Commissioning Phase Sludge<br />

Sampling and Classification<br />

procedure<br />

(PR-TDV-EN-2-N-000-0001).<br />

Transfer Pipeline Hydrostatic Test<br />

and Commissioning Phase<br />

Environmental Discharge Procedure<br />

(PLV-3-EN-PR-0003-00).<br />

Commissioning<br />

Environmental Monitoring<br />

and Control Procedure<br />

(TDV-2-EV-PRD-0006-00)<br />