DC-CIP Design and Construct Community Involvement Plan<br />
DCP Design and Construction Plan<br />
Defects liability<br />
period<br />
Commissioning Environmental Sub-plan (CESP)<br />
This is the period after the completion of the works during which the D&C<br />
Contractor is responsible for any defects. The period is specified in clause 24.6 of<br />
the Deed and is generally 24 months.<br />
DPCD Department of Planning and Community Development<br />
DSE Department of Sustainability and Environment<br />
DSEWPC Department of Sustainability, Environment, Water, Population and Communities<br />
DTS Distributed temperature sensing<br />
DTSJV The <strong>AquaSure</strong> appointed O&M Contractor, Degrémont Thiess Services Joint<br />
Venture<br />
DMPF Dual Media Pressure Filter<br />
DWSS Desalinated Water Supply System, including the marine intake/outlet facilities, the<br />
desalination plant and water transfer pipeline.<br />
EES Environment Effects Statement<br />
Electricity Supplier AGL<br />
EMP Environmental Management Plan. Refers to the D&C EMP and/or AEMP as<br />
relevant in the context of the document<br />
EMR Environmental Management Representative<br />
EMS Environmental Management System<br />
EPA Environment Protection Authority<br />
EPA Section 30A<br />
Commissioning<br />
Approval<br />
Means by which the EPA may authorise emergency storage, use, discharge etc. of<br />
waste under the Environment Protection Act 1970. In the case of VDP this relates<br />
to permitting commissioning activities and associated discharges to the outlet (i.e.<br />
prior to establishment of a licenced mixing zone) – refer to Section 30A(1)(a) and<br />
30A(1A)(c) of the EPA Act.<br />
EPBC Environment Protection and Biodiversity Conservation<br />
Gigalitres (GL) Billion litres<br />
HVAC High Voltage Alternating Current<br />
InCite A web-based document management system managed by Nexus Point Solutions<br />
adopted for use on the <strong>Project</strong>.<br />
ISO 14001 AS/NZS ISO 14001:2004 Environmental Management systems – Requirements<br />
with guidance for use<br />
JSEA Job Safety and Environmental Analysis<br />
MIRA Schedule Monitoring, Inspection, Reporting and Audit Schedule<br />
O&M Operations and Maintenance<br />
O&M Contractor Degrémont Thiess Services Joint Venture<br />
OMMP Operational Marine Monitoring Program<br />
PPEF <strong>Project</strong> Planning and Execution Framework - provides the structure, including a<br />
checklist for preparing Commissioning Work Packs (CWPs).<br />
// Page 7<br />
// TDV-0-EV-SB-0021.I-03