On February 18, <strong>2011</strong>, AAMS sent the concessionaires a “notice of breachof service level agreement”. The notice described the sequence of events todate, and stated that the penalty, calculated according to the terms of thecurrent agreement, the parameters identified by the Technical Commissionand the information contained in the AAMS and Sogei databases, amountedto EUR 46,399,750.00 for the period July 15, 2005 to March 12, 2008,as far as the subsidiary is concerned. However, by applying the other principlesof reasonableness and proportionality required by the Regional AdministrativeTribunal and the Council of State and contained in the last riderto the concession agreement, on the basis of which the penalty for eachyear cannot exceed 11% of the average real remuneration received by theconcessionaire, calculating this remuneration on the basis of certain criteriawhich, however, are open to question, and applying the said percentage tothe result obtained, the disputed penalty amounts to EUR 8,995,332.98.As regards this notice, which did not mention the imposition of a penalty,but only the alleged breach of contract with a reference to the possibleconsequences thereof, the concessionaires filed a defence, objecting to thecontents of the AAMS notice in terms of both substance and form. In particular,the defence stated that there were no delays in the responses of thegateway system and even if there had been any, the blame could not belaid on the concessionaires; during the period in question, the criteria forrecording and calculating penalties had not yet been established by AAMS;the Council of State failed to consider the points raised in the judgmentsissued following the said appeals by the concessionaires; and with specificreference to <strong>Sisal</strong> Slot, amounts which had nothing whatsoever to do withits actual remuneration as a concessionaire were included in the averagereal remunerationAfter the year end, in a document dated January 27, 2012, AAMS servedthe said penalty, quantifying it at EUR 8,995,332.98 and rejecting all thedetailed defence pleas filed by <strong>Sisal</strong> Slot S.p.A.; similar measures have apparentlyalso been taken against all the other concessionaires, and the totalamount of the penalties imposed is believed to amount to approximatelyEUR 70 million.<strong>Sisal</strong> Slot has appealed to the Regional Administrative Tribunal against thisclaim by AAMS, asking firstly for AAMS’ claim to be suspended and, in themain suit, for a ruling that the alleged deficiencies do not exist and that thegranting agency’s calculations are incorrect.In particular, the application of the percentage of 11%, which establishesthe maximum ceiling on the penalties, to the entire turnover of <strong>Sisal</strong> Slotand not just the part relating to income obtained as concessionaire (theremaining part relating to the activity of manager) seems unacceptable andcontrary to the opinions submitted to AAMS by the Council of State andthe Technical Commission; if the calculations were performed correctly, theamount of the penalty would be halved on this ground alone.29 DIRECTORS’ REPORT ON operations
Equally dubious and untrue is AAMS’ allegation that the Technical Commissionbelatedly appointed by AAMS only determined the criteria for calculatingthe penalties, not the criteria for determining what the breach ofcontract consists of in practice.As stated, the ruling also dismisses (on the ground that they relate to differentbreaches of contract) the judgments whereby the Council of Staterecently revoked the first three penalties, relating to the delay with whichthe online network was started up by the concessionaires, and ignoringthe much broader ground, involving the disputes now under discussion,provided by the Council of State (namely the fact that the overall systemimposed by AAMS in 2004/5 clearly had an experimental nature, which waslater reviewed and amended over time).All the technical defences formulated in the defence please were also repeatedin the appeal, together with those emerging from examination ofthe documents supplied by Sogei to AAMS at the end of December.At the hearing held on May 9, 2012, the Regional Administrative Tribunalheard the application for an interlocutory order, suspended the efficacy ofAAMS’ request and set down the case for hearing on February 20, 2013:the reference by the Court to the recent interpretation notices issued by theCouncil of State seems significant, although it was made during interlocutoryproceedings.As regards the case brought before the Court of Auditors, again in relationto the gateway, the Prosecutor of the Court of Auditors asked, in the abovementionedsummons, for the concessionaires to be ordered to pay damagesamounting to the original amount of the alleged loss of Treasury revenues,namely a total of EUR 98 billion for all concessionaires.In the said judgment and order of November 11, 2010, the Court did notagree with the calculation criterion proposed by the Prosecutor, since specificproof would need to be provided that (i) the gateway did not functionproperly, due to the fault of the concessionaires, and (ii) this caused theloss of Treasury revenues (a hypothesis already rejected by the MonorchioCommission).The concessionaires took part in the process conducted by Digit pursuant toItalian Law 241/90, and provided it with all the necessary documentation.On September 30, <strong>2011</strong> Digit filed its technical report with the Court of Auditors.No liability directly attributable to the concessionaires emerged fromthe said report; in particular, no wilful misconduct or negligence was attributeddirectly to them, but it was suggested that they may have contributedto the determination of some critical factors that affected the start-up ofthe gaming system.The concessionaires filed their comments on Digit’s pleading in the Courtof Auditors, and at the hearing held on November 24, <strong>2011</strong>, the Court ofAuditors set down the case for a full hearing.30 <strong>Sisal</strong> ANNUAL REPORT <strong>2011</strong>
- Page 2 and 3: Sisal Annual Report 2011
- Page 6: Finally, we focused on expanding ou
- Page 9 and 10: Group CompaniesSisal Holding Istitu
- Page 12 and 13: Ugo Nespolo, Polvere e basalto (det
- Page 15 and 16: (in million of Euro) 2007 2008 2009
- Page 17 and 18: ne10.3%4,4004,0183,9093,8492,596-16
- Page 19 and 20: co-In the context of a market which
- Page 21 and 22: Within the Group, the aforementione
- Page 23 and 24: • The “convenience services bus
- Page 25 and 26: The excellent level of operating pr
- Page 27 and 28: • In Director’s Decree of Augus
- Page 29: The Court therefore wished to clari
- Page 33 and 34: If the national Court of Auditors s
- Page 35 and 36: Principal risks and uncertainties t
- Page 37 and 38: At the same time the above inspecti
- Page 39 and 40: In December 2011, a general tax ins
- Page 41 and 42: As we know, the tenders for the awa
- Page 43 and 44: Number and nominal value of treasur
- Page 45 and 46: • issue of bank guarantees by the
- Page 47 and 48: Statement of Financial Position - E
- Page 49 and 50: Statement of Changes in EquityATTRI
- Page 51 and 52: Explanatory Notes to the Consolidat
- Page 53 and 54: The second refers to the finalisati
- Page 55 and 56: Translation of financial statements
- Page 57 and 58: Intangible assetsThe intangible ass
- Page 59 and 60: Financial assetsFinancial assets ar
- Page 61 and 62: InventoriesInventories of playslips
- Page 63 and 64: The severance indemnity cost in the
- Page 65 and 66: Any charges related to disputes wit
- Page 67 and 68: Changes in accounting standards ado
- Page 69 and 70: Liquidity riskLiquidity risk is the
- Page 71 and 72: Other informationAs part of a proce
- Page 73 and 74: Property, plant and equipment, as d
- Page 75 and 76: During the course of the year, the
- Page 77 and 78: Intangible assets (3)Intangible ass
- Page 79 and 80: Deferred tax assets (5)The informat
- Page 81 and 82:
Inventories of finished goods and m
- Page 83 and 84:
Current financial assets (10)Curren
- Page 85 and 86:
Cash and cash equivalents (13)Cash
- Page 87 and 88:
The plans thus structured co-exist
- Page 89 and 90:
Sisal S.p.A.Amortisation PlanResidu
- Page 91 and 92:
Deferred tax liabilities (17)The in
- Page 93 and 94:
C) Current LiabilitiesTrade and oth
- Page 95 and 96:
Payables for winnings include jackp
- Page 97 and 98:
Taxation payable (25)Taxation payab
- Page 99 and 100:
Categories of financial assets and
- Page 101 and 102:
ReclassificationThe Group has not c
- Page 103 and 104:
• Other receivables include insur
- Page 105 and 106:
Market riskMarket risk is the risk
- Page 107 and 108:
Notes to the Statementof Comprehens
- Page 109 and 110:
Purchases of materials, consumables
- Page 111 and 112:
Lease and rent expenses (32)These e
- Page 113 and 114:
Finance income and similar (36)Fina
- Page 115 and 116:
Annex 1List of Companies Included i
- Page 117 and 118:
116 SISAL ANNUAL REPORT 2011
- Page 119 and 120:
Sisal Holding Istituto di Pagamento
- Page 121:
Printed by Arti Grafiche MeroniLiss