tender
tender
tender
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
12Clause 42i) (a) Schedule/statement for determining Delhi schedule of rates 2012, CPWDtheoretical quantity of cement &bitumen on the basis of Delhiii) Variations permissible on theoretical quantitiesa) Cement for works with estimated cost putto <strong>tender</strong> not more than Rs. 5 lakhs 03%For works with estimated cost putto <strong>tender</strong> more than 5 Lakhs. 02%b) Bitumen for all works. ----c) Steel reinforcement and structural steel 02%sections for each diameter, section andcategoryRECOVERY RATES FOR QUANTITIES BEYOND PERMISSIBLE VARIATIONS. No. Description of Item Rates in figures and words at which recovery shall bemade from the contractorsExcess beyondpermissible variationLess use beyondThe permissible variation1.CementNARs. 11,000/- Per M.T2.Steel reinforcementNARs. 76,000/- (RupeesSeventy six thousand only)per M.T (subject toacceptance of quality bythe competent authority)