13.07.2015 Views

156 Toll Road Study and Appendices - Transportation Agency for ...

156 Toll Road Study and Appendices - Transportation Agency for ...

156 Toll Road Study and Appendices - Transportation Agency for ...

SHOW MORE
SHOW LESS
  • No tags were found...

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

The Route <strong>156</strong> West Corridor Project Approval <strong>and</strong> Environmental Document (PA&ED) wascompleted by Caltrans at the end of January 2013. Approximately $44 million (year-of-accrual)of state <strong>and</strong> federal funding is allocated to this project at this time, including the costs <strong>for</strong> thecompleted PA&ED. There is a significant funding gap to complete the Route <strong>156</strong> West CorridorProject up to $225 million (in year-of-expenditure dollars, <strong>for</strong> Phase 1 <strong>and</strong> 2.What implications does tolling have to the projectschedule <strong>and</strong> budget?The current Route <strong>156</strong> West Corridor Phase 1 project schedule assumes that Plans Specifications<strong>and</strong> Estimates (PS&E) will begin in the beginning of year 2013, resulting in a bid package beingcompleted by December 2015. If funded, construction would be per<strong>for</strong>med from the middleof year 2016 through year 2019. However, with a Route <strong>156</strong> West Corridor Phase 1 fundinggap of up to $65 million, it is unknown when the Highway <strong>156</strong> improvements would actuallybe constructed.This "sketch-level" analysis, a high-level investigation into the revenue potential, is the first step todetermine if the Highway <strong>156</strong> toll road project is financially feasible. The implementation of atoll road would require additional analysis <strong>and</strong> studies to be completed including a SupplementalEnvironmental Document, as well as an Investment Grade Traffic <strong>and</strong> Revenue <strong>Study</strong>. Publicinvolvement/outreach will be an integral part of the study process <strong>and</strong> would be used to keepthe public in<strong>for</strong>med <strong>and</strong> measure local support. The additional studies <strong>and</strong> public involvementare anticipated to have some impacts to the overall project schedule. Table 2, Modified Route<strong>156</strong> West Corridor Schedule (Phase 1 Only) demonstrates the modifications to the projectschedule as a consequence of advancing Highway <strong>156</strong> as a toll facility.The modified schedule demonstrates that PS&E will begin in the beginning of year 2015, resultingin a bid package being completed by December 2017. Construction would be per<strong>for</strong>med fromthe middle of year 2018 to the end of year 2020.The project capital costs must be adjusted based on the modified schedule to determine howmuch capital cost is required to be paid <strong>for</strong> by tolls. Assuming the st<strong>and</strong>ard Caltrans inflationrates of 3.5% <strong>and</strong> 5% <strong>for</strong> construction <strong>and</strong> right of way, respectively, the construction cost <strong>for</strong>Route <strong>156</strong> West Corridor Phase 1 is anticipated to be $70M in year-of-expenditure dollars.STATE ROUTE <strong>156</strong> <strong>Toll</strong>ing Traffic <strong>and</strong> Revenue <strong>Study</strong> [ 5 ]

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!