Final RFP - IT Hardware for e-Secretariat & other Projects<br />
e) The number <strong>of</strong> firms qualified in technical evaluation, if less than three and it is considered<br />
necessary by the procuring entity to continue with the procurement process, reasons shall<br />
be recorded in writing and included in the record <strong>of</strong> the procurement proceedings.<br />
f) The bidders who qualified in the technical evaluation shall be informed in writing about the<br />
date, time and place <strong>of</strong> opening <strong>of</strong> their financial Bids.<br />
15) Evaluation & Tabulation <strong>of</strong> Financial Bids<br />
Subject to the provisions <strong>of</strong> “Acceptance <strong>of</strong> Successful Bid and Award <strong>of</strong> Contract” below, the<br />
procuring entity shall take following actions for evaluation <strong>of</strong> financial Bids:-<br />
a) The Financial Bids <strong>of</strong> the bidders who qualified in technical evaluation shall be opened<br />
online at the notified time, date and place by the bid evaluation committee in the presence<br />
<strong>of</strong> the bidders or their representatives who choose to be present;<br />
b) the process <strong>of</strong> opening <strong>of</strong> the financial Bids shall be similar to that <strong>of</strong> technical Bids.<br />
c) the names <strong>of</strong> the bidders, the rates given by them and conditions put, if any, shall be read<br />
out and recorded;<br />
d) conditional Bids are liable to be rejected;<br />
e) the evaluation shall include all costs and all taxes and duties applicable to the bidder as<br />
per law <strong>of</strong> the Central/ State <strong>Government</strong>/ Local Authorities, and the evaluation criteria<br />
specified in the bidding documents shall only be applied;<br />
f) the <strong>of</strong>fers shall be evaluated and marked L1, L2, L3 etc. L1 being the lowest <strong>of</strong>fer and then<br />
others in ascending order;<br />
g) the bid evaluation committee shall prepare a comparative statement in tabular form in<br />
accordance with rules along with its report on evaluation <strong>of</strong> financial Bids and recommend<br />
the lowest <strong>of</strong>fer for acceptance to the procuring entity, if price is the only criterion, or most<br />
advantageous Bid in other case;<br />
h) The members <strong>of</strong> bids evaluation committee shall give their recommendations below the<br />
table regarding lowest Bid or most advantageous Bid and sign it.<br />
i) it shall be ensured that the <strong>of</strong>fer recommended for sanction is justifiable looking to the<br />
prevailing market rates <strong>of</strong> the goods, works or service required to be procured.<br />
16) Correction <strong>of</strong> Arithmetic Errors in Financial Bids<br />
The bid evaluation committee shall correct arithmetical errors in substantially responsive Bids,<br />
on the following basis, namely: -<br />
a) if there is a discrepancy between the unit price and the total price that is obtained by<br />
multiplying the unit price and quantity, the unit price shall prevail and the total price shall<br />
be corrected, unless in the opinion <strong>of</strong> the bid evaluation committee there is an obvious<br />
Page 25 <strong>of</strong> 90