Final RFP - IT Hardware for e-Secretariat & other Projects<br />

e) The number <strong>of</strong> firms qualified in technical evaluation, if less than three and it is considered<br />

necessary by the procuring entity to continue with the procurement process, reasons shall<br />

be recorded in writing and included in the record <strong>of</strong> the procurement proceedings.<br />

f) The bidders who qualified in the technical evaluation shall be informed in writing about the<br />

date, time and place <strong>of</strong> opening <strong>of</strong> their financial Bids.<br />

15) Evaluation & Tabulation <strong>of</strong> Financial Bids<br />

Subject to the provisions <strong>of</strong> “Acceptance <strong>of</strong> Successful Bid and Award <strong>of</strong> Contract” below, the<br />

procuring entity shall take following actions for evaluation <strong>of</strong> financial Bids:-<br />

a) The Financial Bids <strong>of</strong> the bidders who qualified in technical evaluation shall be opened<br />

online at the notified time, date and place by the bid evaluation committee in the presence<br />

<strong>of</strong> the bidders or their representatives who choose to be present;<br />

b) the process <strong>of</strong> opening <strong>of</strong> the financial Bids shall be similar to that <strong>of</strong> technical Bids.<br />

c) the names <strong>of</strong> the bidders, the rates given by them and conditions put, if any, shall be read<br />

out and recorded;<br />

d) conditional Bids are liable to be rejected;<br />

e) the evaluation shall include all costs and all taxes and duties applicable to the bidder as<br />

per law <strong>of</strong> the Central/ State <strong>Government</strong>/ Local Authorities, and the evaluation criteria<br />

specified in the bidding documents shall only be applied;<br />

f) the <strong>of</strong>fers shall be evaluated and marked L1, L2, L3 etc. L1 being the lowest <strong>of</strong>fer and then<br />

others in ascending order;<br />

g) the bid evaluation committee shall prepare a comparative statement in tabular form in<br />

accordance with rules along with its report on evaluation <strong>of</strong> financial Bids and recommend<br />

the lowest <strong>of</strong>fer for acceptance to the procuring entity, if price is the only criterion, or most<br />

advantageous Bid in other case;<br />

h) The members <strong>of</strong> bids evaluation committee shall give their recommendations below the<br />

table regarding lowest Bid or most advantageous Bid and sign it.<br />

i) it shall be ensured that the <strong>of</strong>fer recommended for sanction is justifiable looking to the<br />

prevailing market rates <strong>of</strong> the goods, works or service required to be procured.<br />

16) Correction <strong>of</strong> Arithmetic Errors in Financial Bids<br />

The bid evaluation committee shall correct arithmetical errors in substantially responsive Bids,<br />

on the following basis, namely: -<br />

a) if there is a discrepancy between the unit price and the total price that is obtained by<br />

multiplying the unit price and quantity, the unit price shall prevail and the total price shall<br />

be corrected, unless in the opinion <strong>of</strong> the bid evaluation committee there is an obvious<br />

Page 25 <strong>of</strong> 90