Final RFP - IT Hardware for e-Secretariat & other Projects<br />

i) In case <strong>of</strong> Site not ready, the payment to the supplier shall be released for actual number<br />

<strong>of</strong> items installed and commissioned under respective lot. The payment for rest <strong>of</strong> the items<br />

which are not installed and commissioned by the supplier shall be released only after their<br />

installation and commissioning at the respective site.<br />

2) Service Level Standards/ Requirements/ Agreement<br />

Mean Time to Resolve (MTTR) a reported<br />

complaint<br />

Within 72 hours <strong>of</strong> lodging the complaint<br />

Penalty to be deducted from yearly<br />

payable amount<br />

>72 hours <strong>of</strong> lodging the complaint 0.5% <strong>of</strong> the value <strong>of</strong> the item for every 24<br />

working hours past after expiring <strong>of</strong> 72<br />

working hours <strong>of</strong> lodging the complaint<br />

Note: Maximum applicable penalty/ damages shall not exceed 1% <strong>of</strong> the total order value in<br />

an year. In the event <strong>of</strong> any two such consecutive years where the maximum penalty is<br />

imposed on the SI, the event shall be treated as breach <strong>of</strong> contract by DoIT&C.<br />

NIL<br />

Page 57 <strong>of</strong> 90