4.3.3 Obstacle Limitation Surfaces<br />
The following obstacle limitation surfaces shall be established, in accordance<br />
with ICAO standards, for a precision approach runway category I:<br />
a) Conical surface;<br />
b) Inner horizontal surface;<br />
c) Approach surface;<br />
d) Transitional surfaces; and<br />
e) Take-off climb surface<br />
The following obstacle limitation surfaces are also recommended to be<br />
established by ICAO for a precision approach runway category I:<br />
a) Inner approach surface;<br />
b) Inner transitional surfaces;<br />
c) Balked landing surface:<br />
It is recommended that existing objects above these surface should, as far as<br />
practicable, be removed except when an object is shielded by an existing<br />
immovable object, or the object would not adversely affect the safety or<br />
regularity of aircraft operation. The dimensions of obstacle limitation surfaces<br />
are shown in Figure 4-3-1.<br />
4-7