4.9 RESCUE AND FIRE FIGHTING SERVICES<br />

The level of protection for rescue and fire fighting is determined based on the<br />

dimensions of aircraft using the airport in accordance with “<strong>Airport</strong> Service Manual Part<br />

I - Rescue and Fire Fighting” (ICAO). The category for A320 design aircraft is 6. The<br />

minimum usable amounts of extinguishing agents and fire fighting vehicles required for<br />

category 6 are as follows:<br />

Table 4.9-1 Minimum Usable Amount of Extinguishing Agents & Fire Fighting Vehicles<br />

Requirements for Category 6<br />

Min. Number of Rescue and Fire Fighting Vehicles 2<br />

Min Storage of Extinguishing Agents<br />

Water (liters)<br />

11,800<br />

Discharge Rate (Foam Solution/min)<br />

6,000<br />

Complementary Agents<br />

Dry Chemical Powder (kgs.)<br />

225<br />

4.10 AIRPORT UTILITIES<br />

The demand for airport utilities is estimated based on the average unit demands of<br />

airports and summarized in Table 4.10-1.<br />

Table 4.10-1 Unit Demand for Utilities for Planning Purposes<br />

Utilities Area of Application Unit Demand<br />

Water and<br />

Sewage<br />

Passenger Terminal Building<br />

Cargo Terminal Building<br />

Administration Building and Other Buildings<br />

23 liters/sq.m./day<br />

3 liters/sq.m./day<br />

10 liters/sq.m./day<br />

Passenger Terminal Building 0.07 kgs/sq.m./day<br />

Solid Waste Cargo Terminal Building 0.14 kgs/sq.m./day<br />

Administration Building and Other Buildings 0.14 kgs/sq.m./day<br />

Passenger Terminal Building 100 VA/sq.m.<br />

Electricity Cargo Terminal Building 60 VA/sq.m.<br />

Administration Building and Other Buildings 80 VA/sq.m.<br />

Passenger Terminal Building 0.005 extension/sq.m.<br />

Telephone<br />

Cargo Terminal Building<br />

Administration Building and Other Buildings<br />

0.005 extension/sq.m.<br />

0.025 extension/sq.m<br />

Trunk Lines<br />

25 lines<br />

Basis : Average Unit Demand from Mactan, Manila and Narita <strong>Airport</strong>s<br />

Note: Generated Sewage is assumed at 100 % of Water Consumption<br />

Secondary power supply will be estimated to provide emergency power to essential<br />

facilities and equipment at the airport to maintain operation during power failure.<br />

4-14