20.12.2012 Views

MED Communication Handbook - Programme Med

MED Communication Handbook - Programme Med

MED Communication Handbook - Programme Med

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

� European Commission<br />

� European Parliament<br />

� Committee of the Regions<br />

� Member States<br />

� Relevant ministries<br />

� Other relevant national bodies<br />

� Specialised EU networks<br />

� ….<br />

The Influence/Interest grid<br />

A good way to create a stakeholder map is the Influence/Interest Grid (I/I Grid),<br />

which shows us at a glance which categories of stakeholder demand priority attention<br />

in our programme.<br />

less interest<br />

more influence<br />

greater interest<br />

We use this grid by inserting the names of groups and significant individuals in the<br />

four quadrants: those who have considerable influence but not much interest in our<br />

project go in the top-left quadrant; those with both influence and interest go in the<br />

top-right; those with less influence and less interest go in the lower-left, and those<br />

with a lot of interest but little influence go in the lower-right. There should be<br />

between five and ten names in each quadrant. Clearly, the priorities for our<br />

programme are those in the upper-right quadrant.<br />

We use opinion research to create a benchmark for each stakeholder category. This<br />

tells us if the general opinion in the group is positive, neutral or negative. Likewise<br />

less influence<br />

4<br />

� Factsheet 2: Target Audiences<br />