NORSK TOTAL KONTRAKT 20<strong>07</strong> <strong>MOD</strong>IFIKASJON - <strong>NTK</strong> <strong>07</strong> <strong>MOD</strong> - NORWEGIAN TOTAL CONTRACT 20<strong>07</strong> <strong>MOD</strong>IFICATION<br />

ellers slike undersøkelser som en samvittighetsfull<br />

kjøper vil foreta. Leverandøren skal gi Selskapet<br />

varsel straks en mangel oppdages.<br />

6.3 Har ikke Leverandøren varslet Selskapet i henhold til<br />

art. 6.1 eller 6.2 om mangler og uoverensstemmelser<br />

som er oppdaget, og Selskapet som følge av dette<br />

påføres ekstra utgifter i forbindelse med Arbeidet som<br />

ikke er dekket av forsikring, eller taper rettigheter eller<br />

garantier, skal alle slike omkostninger som følger av<br />

dette bæres av Leverandøren. Det samme gjelder<br />

dersom slike mangler og uoverensstemmelser burde<br />

ha vært oppdaget gjennom Leverandørens<br />

kvalitetsstyringssystem eller ved slike undersøkelser<br />

som nevnt i art. 6.2.<br />

6.4 Etter å ha mottatt varsel fra Leverandøren i henhold<br />

til art. 6.1 eller 6.2, skal Selskapet uten ugrunnet<br />

opphold enten sørge for nødvendig retting eller gi<br />

Leverandøren instruks om hvorledes han skal<br />

forholde seg. Reglene i art. 12 til 16 gjelder<br />

tilsvarende.<br />

Art. 7 LEVERANDØRENS SPESIFIKASJON<br />

7.1 Leverandøren skal oppfylle alle krav som følger av<br />

Vedlegg I.<br />

Leverandøren skal uten ugrunnet opphold underrette<br />

Selskapet om mangler og uoverensstemmelser som<br />

oppdages i Vedlegg I. Leverandøren skal omgående<br />

rette disse med mindre Selskapet gir annen instruks i<br />

henhold til art. 12 til 16 eller ved bruk av<br />

avviksprosedyren i Vedlegg D. Leverandørens<br />

rettelser av mangler og uoverensstemmelser i<br />

Vedlegg I skal ikke anses som Endring av Arbeidet.<br />

Art. 8 UNDERLEVERANSER<br />

8.1 Leverandøren skal ikke inngå kontrakt om<br />

Underleveranser for deler av Arbeidet uten at<br />

Selskapet på forhånd har gitt samtykke. Selskapet<br />

skal gi Leverandøren meddelelse om sitt standpunkt<br />

senest 7 Dager etter at Leverandøren har bedt om<br />

det. Samtykke trengs likevel ikke for leverandører<br />

som er nevnt i Vedlegg H, mindre innkjøp og bruk av<br />

leiet arbeidskraft i begrenset omfang.<br />

Leverandøren skal anskaffe Materialer ved bruk av de<br />

Rammeavtaler som er angitt i Vedlegg E med mindre<br />

det der er bestemt at Leverandøren står fritt.<br />

8.2 Leverandøren er ansvarlig etter Kontrakten for<br />

Underleveranser. Dette gjelder også<br />

Underleveranser bestilt ved bruk av Rammeavtaler.<br />

8.3 For Underleveranser bestilt ved bruk av<br />

Rammeavtaler som Leverandøren er pålagt å<br />

benytte, gjelder:<br />

- 10 -<br />

in Appendix D, and any such other examination as a<br />

conscientious purchaser would carry out. Contractor<br />

shall notify Company promptly of any defects<br />

discovered.<br />

6.3 If Contractor has not notified Company in<br />

accordance with Art. 6.1 or 6.2 of any defects,<br />

discrepancies and inconsistencies discovered, and<br />

as a result, Company incurs direct extra costs in<br />

connection with the Work which are not covered by<br />

insurance, or loses rights or guarantees, then all<br />

such costs incurred shall be borne by Contractor.<br />

The same shall apply if such defects, discrepancies<br />

and inconsistencies ought to have been discovered<br />

through Contractor's quality management system or<br />

by such inspections as are stated in Art. 6.2.<br />

6.4 Upon receipt of notice from Contractor in<br />

accordance with Art. 6.1 or 6.2, Company shall,<br />

without undue delay, either have the necessary<br />

corrections made, or give Contractor instructions on<br />

how to proceed. The provisions of Art. 12 to 16 shall<br />

apply accordingly.<br />

Art. 7 CONTRACTOR'S SPECIFICATION<br />

7.1 Contractor shall comply with all requirements<br />

following from Appendix I.<br />

Contractor shall notify Company without undue<br />

delay of defects, discrepancies and inconsistencies<br />

discovered in Appendix I. Contractor shall<br />

immediately correct these unless otherwise<br />

instructed by Company in accordance with Art. 12 to<br />

16 or by the use of the procedure given in Appendix<br />

D. Contractor's correction of defects, discrepancies<br />

and inconsistencies in Appendix I shall not be<br />

considered a Variation to the Work.<br />

Art. 8 SUBCONTRACTORS<br />

8.1 Contractor shall not enter into any contract for<br />

Subsupply concerning parts of the Work without the<br />

prior consent of Company. Company shall notify<br />

Contractor of its decision within seven Days after<br />

having been asked by Contractor. However, such<br />

consent is not required for contractors listed in<br />

Appendix H, minor purchases or limited use of hired<br />

labour.<br />

Contractor shall procure Materials by making use of<br />

the Frame Agreements listed in Appendix E unless<br />

therein provided that Contractor is not so obliged.<br />

8.2 Contractor is responsible according to the Contract<br />

for Subsupplies. This also applies to Subsupplies<br />

ordered on the basis of Frame Agreements.<br />

8.3 The following applies to Subsupplies ordered on the<br />

basis of Frame Agreements which Contractor is<br />

obliged to use: