NORSK TOTAL KONTRAKT 20<strong>07</strong> <strong>MOD</strong>IFIKASJON - <strong>NTK</strong> <strong>07</strong> <strong>MOD</strong> - NORWEGIAN TOTAL CONTRACT 20<strong>07</strong> <strong>MOD</strong>IFICATION<br />
23.2 Garantiperioden begynner når Leveringsprotokoll<br />
opprettes, og utløper to år deretter.<br />
Hvis art. 19.5 kommer til anvendelse vil<br />
Garantiperioden for de Prefabrikkerte Materialer<br />
starte ved levering i henhold til art. 19.5 b), og den<br />
utløper:<br />
a) for Prefabrikkerte Materialer levert tidligere enn<br />
levering av Modulen(e): samtidig med utløpet av<br />
Garantiperioden for Modulen(e).<br />
b) for Prefabrikkerte Materialer levert etter levering<br />
av Modulen(e); samtidig med utløpet av<br />
Garantiperioden for Offshore<br />
Modifikasjonsarbeidet.<br />
23.3 Har Leverandøren utført garantiarbeider i<br />
Garantiperioden, har han garantiansvar etter art. 23.1<br />
for de deler av Arbeidet som utbedringen omfatter.<br />
Dette ansvar gjelder i ett år fra datoen for fullføringen<br />
av garantiarbeidet med mindre den gjenstående del<br />
av Garantiperioden er lengre. Garantitiden for slike<br />
deler av Arbeidet skal likevel ikke i noe tilfelle være<br />
mer enn to år fra den dato da den første utbedringen<br />
var fullført.<br />
23.4 Selskapet skal ha rett til å gjøre gjeldende de<br />
garantier Underleverandører har gitt til Leverandøren.<br />
23.5 Selskapet skal utstede Godkjennelsesattest når<br />
Arbeidet inklusive garantiarbeider er fullført.<br />
Godkjennelsesattesten skal anses utstedt 30 Dager<br />
etter utløp av Garantiperioden eller av den periode<br />
som er nevnt i art. 23.3 dersom den utløper senere.<br />
DEL VI KONTRAKTSBRUDD<br />
Art. 24 FORSINKELSE FRA LEVERANDØRENS SIDE<br />
24.1 Ut over det som er fastlagt om forsinket fremdrift i art.<br />
11, foreligger forsinkelse når det Arbeid Vedlegg C<br />
forutsetter ikke er kontraktsmessig utført på<br />
tidspunktet for en dagmulktsanksjonert milepæl.<br />
I forhold til Leveringsdato skal levering anses å ha<br />
skjedd på det tidspunkt da Leveringsprotokollen<br />
opprettes eller skulle ha vært opprettet i henhold til<br />
art. 19.1 og 19.2.<br />
24.2 Er Arbeidet forsinket i forhold til de<br />
dagmulktsanksjonerte milepæler som er fastsatt i<br />
Vedlegg C, skal Leverandøren betale dagmulkt til<br />
Selskapet. Dersom milepælen for Mekanisk<br />
Ferdigstillelse oppnås, bortfaller likevel Selskapets<br />
rett til dagmulkt for forsinkelse i relasjon til de tidligere<br />
- 32 -<br />
23.2 The Guarantee Period commences at the<br />
conclusion of the Delivery Protocol and expires two<br />
years thereafter.<br />
If Art. 19.5 apply, the Guarantee Period for the<br />
Prefabricated Items commences when delivery<br />
occurs in accordance with Art. 19.5 b), and it<br />
expires:<br />
a) for Prefabricated Items delivered prior to delivery<br />
of the Module(s); simultaneously with the<br />
expiration of the Guarantee Period for the<br />
Module(s),<br />
b) for Prefabricated Items delivered after delivery of<br />
the Module(s); simultaneously with the expiration<br />
of the Guarantee Period for the Offshore<br />
Permanent Works.<br />
23.3 In case Contractor performs guarantee work during<br />
the Guarantee Period, he guarantees according to<br />
Art. 23.1 those parts of the Work affected by the<br />
guarantee work. This guarantee applies for one year<br />
after the date of completion of the guarantee work,<br />
unless the remaining part of the Guarantee Period is<br />
longer. The length of the guarantee for such parts of<br />
the Work shall, however, under no circumstances<br />
extend beyond two years after the completion of the<br />
first guarantee work.<br />
23.4 Company shall be entitled to enforce the guarantees<br />
given by Subcontractors to Contractor.<br />
23.5 Company shall issue an Acceptance Certificate<br />
when the Work, including guarantee work, has been<br />
completed. The Acceptance Certificate shall be<br />
deemed to have been issued 30 Days after the<br />
latest of the expiry of the Guarantee Period or of the<br />
period set out in Art. 23.3.<br />
PART VI BREACH OF CONTRACT<br />
Art. 24 CONTRACTOR'S DELAY<br />
24.1 Save what is stated in Art. 11 concerning delayed<br />
progress, delay occurs when the Work prescribed in<br />
Appendix C has not been completed in accordance<br />
with the Contract by a penalty milestone.<br />
In relation to the Delivery Date, delivery shall be<br />
deemed to have taken place at the conclusion of the<br />
Delivery Protocol, or at the time it should have been<br />
concluded in accordance with Art. 19.1 and 19.2.<br />
24.2 If the Work is delayed in relation to the penalty<br />
milestones set forth in Appendix C, then Contractor<br />
shall pay liquidated damages to Company. If,<br />
however, the milestone for Mechanical Completion<br />
is met, then Company's right to be paid liquidated<br />
damages for such earlier delay ceases, unless and