NORSK TOTAL KONTRAKT 20<strong>07</strong> <strong>MOD</strong>IFIKASJON - <strong>NTK</strong> <strong>07</strong> <strong>MOD</strong> - NORWEGIAN TOTAL CONTRACT 20<strong>07</strong> <strong>MOD</strong>IFICATION<br />
18.2 Selskapet skal erstatte Leverandøren alle<br />
nødvendige kostnader ved:<br />
a) demobilisering av personell, utstyr og<br />
Byggeplass(er), og<br />
b) sikring av Kontraktsgjenstanden, Materialer og<br />
Selskapsmaterialer, og<br />
c) personell, Underleverandører og utstyr som må<br />
holdes tilgjengelig i henhold til<br />
mobiliseringsplanen, og<br />
d) nødvendig flytting av Kontraktsgjenstanden for å<br />
unngå urimelig ulempe for Leverandørens øvrige<br />
virksomhet, og<br />
e) andre kostnader Leverandøren har hatt som følge<br />
av innstillingen av Arbeidet.<br />
Leverandørens krav for arbeid som utføres skal så<br />
vidt mulig beregnes etter prinsippene i art. 13.2, og<br />
Kontraktsprisen skal justeres tilsvarende. Betaling<br />
skal skje i samsvar med reglene i art. 20.<br />
18.3 Vedlegg C skal justeres for virkningen av innstillingen<br />
av Arbeidet. Art. 12 til 16 gjelder tilsvarende.<br />
Endringsordrekrav må fremsettes uten ugrunnet<br />
opphold etter at Selskapet har krevd Arbeidet<br />
gjenopptatt.<br />
18.4 Hvis Arbeidet eller deler av det har vært innstilt uten<br />
avbrudd i mer enn 120 Dager, kan Leverandøren med<br />
14 Dagers varsel si opp Kontrakten for så vidt angår<br />
den del av Arbeidet som er innstilt. Har Selskapet<br />
ikke innen 14 Dager etter at varselet ble mottatt, gitt<br />
ordre om gjenopptagelse av Arbeidet, gjelder<br />
bestemmelsene i art. 17 tilsvarende.<br />
18.5 Selskapet har ikke rett til midlertidig innstilling for en<br />
lengre periode enn angitt i Vedlegg C av de deler av<br />
Arbeidet som er omfattet av en kontrakt om<br />
Underleveranse av marine tjenester ved<br />
sammenkoblingsoperasjoner, tungløftoperasjoner<br />
eller installasjon av Kontraktsgjenstanden.<br />
DEL V LEVERING OG BETALING<br />
Art. 19 LEVERING OG FULLFØRING AV ARBEIDET<br />
19.1 Levering av Kontraktsgjenstanden skjer ved at<br />
partene i fellesskap etter krav fra Leverandøren<br />
oppretter Leveringsprotokoll når Leveringsdato er<br />
nådd, og Kontraktsgjenstanden er ferdig, har<br />
gjennomgått de tester som Kontrakten foreskriver og<br />
er klar for levering.<br />
Leveringsprotokollen skal opprettes selv om mindre<br />
deler av Arbeidet gjenstår, forutsatt at disse ikke har<br />
- 23 -<br />
18.2 Company shall compensate Contractor for all<br />
necessary expenses arising from:<br />
a) demobilization of personnel, equipment and<br />
Site(s), and<br />
b) safeguarding the Contract Object, Materials and<br />
Company’s Materials, and<br />
c) personnel, Subcontractors and equipment which<br />
must be kept available in accordance with the<br />
mobilization plan, and<br />
d) moving the Contract Object, if necessary, to<br />
avoid unreasonable interference with<br />
Contractor's other activities, and<br />
e) other expenses incurred by Contractor as a<br />
result of the suspension of the Work.<br />
Contractor's claim for work performed shall be<br />
calculated as far as possible in accordance with the<br />
principles of Art. 13.2, and the Contract Price shall<br />
be adjusted accordingly. Payment shall be made in<br />
accordance with the provisions in Art. 20.<br />
18.3 Appendix C shall be adjusted for the consequences<br />
of the suspension of the Work. Art. 12 to 16 shall<br />
apply accordingly. A Variation Order Request must<br />
be submitted without undue delay after Company<br />
has requested that the Work be resumed.<br />
18.4 If the Work or parts thereof have been suspended<br />
continuously for a period exceeding 120 Days, then<br />
Contractor may cancel the Contract for that part of<br />
the Work which is suspended by giving 14 Days<br />
notice. If Company has not ordered a resumption of<br />
the Work within 14 Days after receiving the notice,<br />
then the provisions of Art. 17 shall apply<br />
accordingly.<br />
18.5 Company is not entitled to a temporary suspension<br />
for a longer period than stated in Appendix C of<br />
those parts of the Work that are included in a<br />
contract for Subsupply of marine operations related<br />
to mating, heavy lifts or installation of the Contract<br />
Object.<br />
PART V DELIVERY AND PAYMENT<br />
Art. 19 DELIVERY AND COMPLETION OF THE WORK<br />
19.1 Delivery of the Contract Object occurs when the<br />
parties jointly, upon Contractor's request, conclude<br />
a Delivery Protocol when the Delivery Date has<br />
been reached, the Contract Object has been<br />
completed, has passed the tests specified in the<br />
Contract, and is ready for delivery.<br />
The Delivery Protocol shall be concluded even if<br />
minor parts of the Work remain incomplete,