24.02.2013 Views

Section 1 Introduction - National Marine Fisheries Service - NOAA

Section 1 Introduction - National Marine Fisheries Service - NOAA

Section 1 Introduction - National Marine Fisheries Service - NOAA

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

NBK at Bangor EHW-1 Pile Replacement Project Final <strong>Marine</strong> Mammal Monitoring Report<br />

Extrapolated Level B Takes for the Unmonitored Zone<br />

The measured behavioral harassment zone during vibratory pile installation and removal, defined<br />

as the area within the average distance to the 120 dB isopleth during the EHW-1 PRP (calculated<br />

as a 2.7 miles [4.4 km] radius from the construction location), covered 8.8 mi 2 (22.84 km 2 ).<br />

Only a subset of this area was monitored (1.5 miles [2.4 km] radius from the pile, or 4 mi 2<br />

[10.32 km 2 ]) because of logistical constraints. It is therefore appropriate to estimate the number<br />

of potential Level B marine mammal takes that may have occurred in the ensonfied, but<br />

unmonitored, zone. To extrapolate missed takes, species density in Hood Canal (individuals<br />

observed during EHW-1 per km² per hr) was multiplied by the unmonitored area that fell within<br />

the measured harassment zone. The product of these two numbers represents the estimated<br />

density (individuals/km²/hr) in the unmonitored zone. Species density in the unmonitored zone<br />

was then multiplied by the total number of construction hours during the EHW-1 PRP to arrive at<br />

an estimate of the numbers of takes missed in the unmonitored, ensonified zone (Table 11).<br />

Only sighting rates from outside the WRA were considered in the analysis, since these were<br />

likely more representative of animal densities in the unmonitored zone. It should be noted that<br />

the density estimates were not collected using standard line-transect methodology, since at the<br />

time of writing these data were not available for Hood Canal for all species in question. Using<br />

the methods outlined above, it is estimated that approximately 5 harbor porpoise, 8 harbor seals,<br />

30 California sea lions and 1 Steller sea lion were “taken” in the unmonitored section of the<br />

behavioral harassment zone for marine mammals.<br />

Table 11. Missed Takes in the Unmonitored Area of the Behavioral Harassment Zone<br />

Species<br />

Density<br />

Estimate<br />

Measured<br />

Level B<br />

Harassment<br />

Zone<br />

(Area, km²)<br />

Monitored<br />

Area<br />

(km²)<br />

Unmonitored<br />

Harassment<br />

Zone<br />

(Area, km²)<br />

Estimated<br />

Density in<br />

Unmonitored<br />

Area<br />

Total<br />

Construction<br />

Hours During<br />

EHW-1<br />

Missed<br />

Takes<br />

(Estimated)<br />

Harbor porpoise 0.032<br />

0.40<br />

4.96<br />

Harbor seal<br />

California sea lion<br />

0.048<br />

0.195<br />

22.84 10.32 12.52<br />

0..60<br />

2.44<br />

12.4<br />

7.44<br />

30.26<br />

Steller sea lion 0.004 0.05 0.62<br />

<strong>Marine</strong> Mammal Mitigation Procedures: Construction Delays and Shutdowns<br />

In most cases, when a marine mammal was observed in the 164 ft (50 m) shutdown zone,<br />

ongoing construction was shut down, and imminent construction was delayed. Shutdowns as a<br />

result of pinnipeds inside the 164 ft (50 m) accounted for ten hours and sixteen minutes of delays<br />

throughout the lifetime of the project. In five cases, where cessation of pile driving posed a<br />

safety hazard, construction was allowed to continue even though a marine mammal was sighted<br />

within the 164 ft (50 m) shutdown zone (see highlighting in Table 12). Nine piles (EHW-8<br />

through EHW-16) were installed in and under the existing EHW-1 structure, and required the<br />

construction crane, hammer and pilings to be positioned within a few feet of the building.<br />

Because the hammer required delicate positioning over the pile to avoid building damage, in<br />

these situations the construction foreman notified the MC that it was not possible to interrupt the<br />

pile driving event without risk to the crew and to the EHW-1 structure from the piling and/or<br />

vibratory hammer hitting the building.<br />

Bangor, Washington 41

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!