24.02.2013 Views

Section 1 Introduction - National Marine Fisheries Service - NOAA

Section 1 Introduction - National Marine Fisheries Service - NOAA

Section 1 Introduction - National Marine Fisheries Service - NOAA

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

NBK at Bangor EHW-1 Pile Replacement Project Final <strong>Marine</strong> Mammal Monitoring Report<br />

3. No marine mammals were observed within the 164 ft (50 m) EZ during the 3 pulses of<br />

hammer activity associated with soft start of the vibratory hammer.<br />

4. Any marine mammal that entered the 164 ft (50 m) EZ did so of its own volition, and was<br />

therefore, not being injured or frightened by the sound energy being produced by the<br />

hammer.<br />

5. Pile driving was allowed to continue while the MMOs tracked the animal to note its<br />

distance from the pile, and to observe any signs of behavioral distress.<br />

6. If signs of behavioral distress were noted, an all-stop on construction was implemented<br />

(Note: this situation never occurred during EHW-1 construction activities).<br />

All five instances where the “hazardous piling” standard was invoked occurred on 15 and 17<br />

October, and all resulted in Level B harbor seal takes (Tables 10 and 12). There were no Level<br />

A takes for any marine mammal species during the EHW-1 PRP because the average RMS<br />

sound level recorded during construction activity was 166 dB RMS (re: 1µPa) at 10 meters<br />

which would be below the injury thresholds for both pinnipeds and cetaceans at the source.<br />

Even the maximum RMS sound level recorded of 174 dB RMS (re: 1µPa) at 10 meters would be<br />

below the pinnipeds injury threshold of 190 dB RMS at the source and would only be above the<br />

cetacean injury threshold of 180 dB RMS out to less than 4 meters from the pile (NAVFAC<br />

2012). No cetacean ever approached or entered the WRA (over 500 meters from EHW-1)<br />

therefore there was no risk of injury to these species even though the sound pressure levels were<br />

above the 180 dB isopleth on occasion.<br />

During non-hazardous pile driving, there were five construction shutdowns and 20 construction<br />

delays due to: (1) marine mammals (in all cases harbor seals) present in the 164 ft (50 m)<br />

shutdown zone prior to, or during, pile driving activities; or (2) Steller sea lions observed in the<br />

water or moving towards the water while hauled out on submarines at Delta Pier (Figure 5).<br />

Either of these scenarios triggered an automatic shutdown of construction to avoid unauthorized<br />

Level B Steller sea lion takes (Table 10). After 12 October, two MMOs were stationed the Delta<br />

Pier during construction in order to perform regular Steller sea lion counts and behavioral focal<br />

follows. If a Steller sea lion was observed changing from a resting to active behavioral state<br />

while hauled out at Delta pier, the Delta Pier MMO alerted the MC of the potential for a<br />

shutdown via handheld VHF radio. If the animal(s) moved towards the water, the MC<br />

immediately initiated a construction shutdown, or delayed imminent construction (Table 12).<br />

Construction was delayed on 14 October because of a Steller sea lion moving towards the water<br />

from a resting position. Construction was not resumed until the MMO and MC were confident<br />

that the animal did not intend on returning to the water. Construction was delayed again on<br />

15 October because of a Steller sea lion observed in the water prior to construction start, and<br />

construction was not allowed to resume until the animal had left the monitored zone. Ongoing<br />

construction was shut down on 21 October because a Steller sea lion was observed coming out of<br />

the water to haul out on a submarine. The animal approached the submarine from a distance<br />

while remaining underwater, and was therefore unseen by the MMOs until it hauled out, as a<br />

result this observation was recorded as an unauthorized Level B take.<br />

Another four construction shutdowns were triggered on 12 October, 13 October and 27 October<br />

due to a harbor seal observed within the shutdown zone while construction was ongoing. In all<br />

cases, construction was not resumed until the animal had left the area. There were a total of 20<br />

Bangor, Washington 43

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!