The turrets are often individually adapted; check therefore that they are<br />
re-mounted in correct places, which appear from the OGA drawing and ,part<br />
list.<br />
Assembling of bushings is carried out according to the detailed<br />
information documents available.<br />
2.1.9 ASSEMBLY OF VALVES<br />
Valves which may affect the loading gauge, or will be subjected to<br />
damages, should be dismounted before delivery. Re-mount the valves -the<br />
positionings appear from the OGA drawing and part list. The gasketting surfaces<br />
shall be cleaned well and new gaskets fitted. Check that all valves are closed.<br />
2.1.10 ASSEMBLY OF COOLING DEVICES<br />
Valves which are not dismantled like shut-off valves for radiators, coolers<br />
and possible headers shall be provided with blanking plates during the transport.<br />
Remove the blanking plates when the assembling of the coolers is to be<br />
started. Check first that the valves are closed.<br />
Check that each radiator and possible header are assembled in the correct<br />
positions according to OGA drawing. In case of OFAF or OFWF cooler mounting<br />
shall be done as per the relevant leaflet given in Vol.I<br />
The shut-off valves against the transformer tank shall be closed until<br />
the oil-filling is started.<br />
2.1.11 ASSEMBLY OF OIL CONSERVATOR<br />
The conservator, which may be with or without aircell is assembled<br />
either on the transformer, or on a separate frame. Before the conservator is<br />
assembled it shall be checked that belonging equipment -e.g. Oil-level indicator<br />
-functions satisfactorily.<br />
The breather is connected to the oil conservator, and it is very important<br />
that joints and couplings in the pipe between breather and conservator are air<br />
tight. Refer Clause 2.6 for detailed <strong>instruction</strong> for oil filling.<br />
2.1.12 ASSEMBLY OF PIPE WORK<br />
Pipes with flanges for connection of conservator, radiators, as well as<br />
pipes for equalising of turrets etc. are mostly delivered completely ready for<br />
assembling according to OGA & part list.<br />
In certain cases -e.g. at a separately assembled oil conservator -certain<br />
fitting and welding of pipes and flanges on site is however required. Instruction<br />
for such assembly of external pipes is given in Clause 2.3<br />
2.1.13 FLANGES, BLANKING PLATES<br />
When re-mounting blanking plates, connection flanges etc., the gasketting<br />
surface shall be cleaned well and new gaskets fitted.<br />
Prepared By Samvet Lahari, <strong>Bhopal</strong>. Phone- 5277412