2.4.2 SUPPLY AND TESTING<br />

The transformer oil is despatched directly to site from oil refinery. The<br />

oil is thoroughly inspected and tested at oil supplier's works in presence of<br />

<strong>BHEL</strong> and/or customer's representative or their authorised representatives.<br />

Test certificate giving values obtained for all characteristics is issued.<br />

2.4.3 HANDLING<br />

The oil drums should be carefully handled at site, details of which are<br />

given in Clause 9.1of IS:1866.<br />

2.4.4 RECONDITIONING<br />

Transformer oil is usually contaminated during handling, transport and<br />

storage due to ingress of moisture and solid impurities. Hence, oil shall be<br />

vacuum filtered separately at 50 0 C to 60 °C using a suitable filtration machine<br />

and a spare clean tank before filling in the transformer. Details of filtration are<br />

given in Clause 9.2 of IS:1866. Oil treatment shall be terminated when the<br />

following parameters are attained.<br />

TABLE 2.1<br />

kV Class of transformer Recommended Permissible limit<br />

Electric Strength Moisture Content<br />

(BDV) in kV (Min) ppm (Max)<br />

Upto 145 60 20<br />

245 65 15<br />

420 70 15<br />

Storage tank shall be as per typical arrangement shown in Fig 2.2<br />

Electric strength and moisture content shall be determined following<br />

the test procedure of IS: 335.<br />

2.5 OIL FILLING UNDER VACUUM<br />

2.5.1 APPLICATION<br />

Transformers and Reactors with vacuum-proof tanks shall be filled with<br />

oil according to this method.<br />

2.5.2 STORING TIME<br />

Generally it applies that Transformers and reactors which during transport<br />

are filled with dry nitrogen on arrival at the site shall be evacuated and oil<br />

filled. Before storing, the equipment shall be inspected according to the<br />

directions given in Clause 2.1 "Reception and assembling of transformer/reactor<br />

despatched partly dissembled and filled with nitrogen". During the storing<br />

time, overpressure shall be maintained, and nitrogen consumption checked<br />

according Clause 2.2.<br />

Prepared By Samvet Lahari, <strong>Bhopal</strong>. Phone- 5277412