2.4.2 SUPPLY AND TESTING<br />
The transformer oil is despatched directly to site from oil refinery. The<br />
oil is thoroughly inspected and tested at oil supplier's works in presence of<br />
<strong>BHEL</strong> and/or customer's representative or their authorised representatives.<br />
Test certificate giving values obtained for all characteristics is issued.<br />
2.4.3 HANDLING<br />
The oil drums should be carefully handled at site, details of which are<br />
given in Clause 9.1of IS:1866.<br />
2.4.4 RECONDITIONING<br />
Transformer oil is usually contaminated during handling, transport and<br />
storage due to ingress of moisture and solid impurities. Hence, oil shall be<br />
vacuum filtered separately at 50 0 C to 60 °C using a suitable filtration machine<br />
and a spare clean tank before filling in the transformer. Details of filtration are<br />
given in Clause 9.2 of IS:1866. Oil treatment shall be terminated when the<br />
following parameters are attained.<br />
TABLE 2.1<br />
kV Class of transformer Recommended Permissible limit<br />
Electric Strength Moisture Content<br />
(BDV) in kV (Min) ppm (Max)<br />
Upto 145 60 20<br />
245 65 15<br />
420 70 15<br />
Storage tank shall be as per typical arrangement shown in Fig 2.2<br />
Electric strength and moisture content shall be determined following<br />
the test procedure of IS: 335.<br />
2.5 OIL FILLING UNDER VACUUM<br />
2.5.1 APPLICATION<br />
Transformers and Reactors with vacuum-proof tanks shall be filled with<br />
oil according to this method.<br />
2.5.2 STORING TIME<br />
Generally it applies that Transformers and reactors which during transport<br />
are filled with dry nitrogen on arrival at the site shall be evacuated and oil<br />
filled. Before storing, the equipment shall be inspected according to the<br />
directions given in Clause 2.1 "Reception and assembling of transformer/reactor<br />
despatched partly dissembled and filled with nitrogen". During the storing<br />
time, overpressure shall be maintained, and nitrogen consumption checked<br />
according Clause 2.2.<br />
Prepared By Samvet Lahari, <strong>Bhopal</strong>. Phone- 5277412