<strong>CIDCO</strong> <strong>OF</strong> MAHARASHTRA LTD<br />

C.A.No.03/<strong>CIDCO</strong>/EE(Elect)/2011-12 Sr. Page No.<br />

30 m of its underground length with atleast one tag at each end before<br />

the cable enters the ground. In unpaved areas, cable trenches shall be<br />

identified by means of markers as per standard drawing. These posts<br />

shall be placed at location of changers in the direction of cables and at<br />

intervals of not more than 30 m and at cable joint locations.<br />

4.7 All temporary ends of cables must be protected against dirt and moisture<br />

to prevent damage to the insulation. For this purpose, ends of all PVC<br />

insulated cables shall be taped with an approved PVC or rubber insulating<br />

tape. Use of friction type or other fabric type tape is not permitted. Lead<br />

sheathed cables shall be plumbed with lead olloy.<br />

4.8 RCC cable trenches with insert plates shall be provided by the contractor.<br />

Cable shall be laid in 3 to 4 tiers in these trenches.<br />

4.9 Directly buried cables shall be laid underground in excavated cable<br />

trenches where specified and layout drawings. Trenches shall be of<br />

minimum 0.9 mtr. depth and suitable width for accommodation of all<br />

cables correctly spaced and arranged with a view of heat dissipation and<br />

economy of design. Depth of burying shall allow minimum 900 mm soil<br />

cover for low voltage and 1000 mm for 11KV cables.<br />

L.T. cables shall be laid in trenches as above stated depth. Before cables<br />

are placed, the trenches bottom shall be filled with layer of sand. This<br />

sand shall be leveled and the cables laid over it. The cables shall be<br />

covered with 150 mm of sand on top of the largest diameter cable and<br />

sand shall be lightly pressed. A protective covering of 75 mm thick<br />

second class red bricks shall then be laid flat. The remainder of the<br />

trench shall then be back-filled with soil, rammed and leveled.