<strong>CIDCO</strong> <strong>OF</strong> MAHARASHTRA LTD<br />
C.A.No.03/<strong>CIDCO</strong>/EE(Elect)/2011-12 Sr. Page No.<br />
filed to avoid interference with structures, piping or air-conditioning duct<br />
and minor adjustments shall be done to suit the filed conditions wherever<br />
deemed necessary without any extra cost.<br />
4.2 High voltage, medium voltage and other control and communication<br />
cables shall be separated from each other by adequate spacing or running<br />
through independent pipes, trenches or cable trays, as applicable.<br />
4.3 All cable routes shall be carefully measured and cables cut to the required<br />
lengths, leaving sufficient lengths for the final connection of the cable to<br />
the terminal of the equipment. The various cable lengths cut form the<br />
cable reels shall be carefully selected to prevent undue wastage of cables.<br />
The quantity indicated in the cable schedule is only approximate. The<br />
contractor shall ascertain the exact requirement of cable for a particular<br />
feeder by measuring at site and avoiding interference with structure,<br />
foundation, pipelines or any other works.<br />
4.4 Cables as far as possible shall be laid in complete, uncut lengths from one<br />
termination to the other.<br />
4.5 Cables shall be neatly arranged in the trenches/trays in such manner so<br />
that criss-crossing is avoided and final take off to the motor/switchgear is<br />
facilitated. Arrangement of cables within the trench/trays shall be the<br />
responsibility of the contractor.<br />
4.6 All cables will be identified close to their termination point by cable<br />
numbers as per cable schedule. Cable numbers will be punched on<br />
aluminium straps (2 mm thick) securely fastened to the cable and srapped<br />
around it. Alternatively cable tags shall be circular in construction to<br />
which cable numbers can be conveniently punched. Each underground<br />
cable shall be provided with identify tags of lead securely fastened every